Power factor correction
Preview Version 0.1.0How much capacitor correction raises your power factor to a target, and what the low power factor costs on your tariff.
Correction needed
236.8kVAR
Raising 500 kW from 0.78 to 0.95 takes about 236.8 kVAR of correction.
U.S. Department of Energy · Washington State University Energy Program and the Northwest Energy Efficiency AllianceCross-checked · The spec's 236.8 kVAR, 641.0 and 526.3 kVA, and $1,384.62 penalty cases pass, and a target below the current power factor returns no correction. Two published worked examples (DOE and WSU/NEEA) are reproduced within 1 kVAR. What this means
Screening estimate: a capacitor bank's size, steps, and placement, and any harmonic or resonance risk, are an electrical engineer's decision. · Example values · Review pending Report a problem
How we got this
Method
Correction in kVAR is kW × (tan(arccos(PF now)) − tan(arccos(PF target))); apparent power is kW ÷ PF; line current is kVA × 1,000 ÷ (√3 × V) for three-phase service. On a tariff that bills demand scaled to a power-factor threshold, billing kW is kW × threshold ÷ PF when PF is lower.
Steps
- Power factor now: 0.78, as entered.
- Correction: 500 kW × (tan(arccos 0.78) − tan(arccos 0.95)) = 500 × (0.8023 − 0.3287) = 236.8 kVAR.
- Apparent power: 641 kVA now, 526.3 kVA after; current falls by 138 A at 480 V three-phase.
- Tariff: billing demand is 500 kW × 0.9 ÷ 0.78 = 576.9 kW, a power-factor penalty of 76.9 kW, or $1,384.62 a month at $18.00/kW. Correcting to 0.95 removes it.
- The saving is the tariff's power-factor effect only; it leaves out the cost of the equipment and its installation, and any reduction in losses.
- Choose the bank's size, steps, and placement with an electrical engineer, who also checks for harmonics and resonance; no public-domain list of standard bank ratings is cited here, so size up to the next rating your supplier offers.
Assumptions
- The power factor entered (or computed from kVAR or kVA) is the one the utility bills on; a bill or the meter shows it.
- Correction is sized for the kW entered, usually the demand-setting load.
Sources
- U.S. Department of Energy, Energy Efficiency and Renewable Energy, "Reducing Power Factor Cost", Motor Challenge fact sheet, Power triangle example: 100 kW and 100 kVAR, corrected to 0.95 with a 67 kVAR capacitor
- Washington State University Energy Program and the Northwest Energy Efficiency Alliance, "Energy Efficiency Factsheet: Reducing Power Factor Cost" (published by Clark Public Utilities), Factsheet, Figure 4: a 100 kW load at 0.70 corrected to 0.95 with a 69 kVAR capacitor
Known limits
- The power factor is entered or derived from one kW and kVAR or kVA pair; a file with reactive readings gives a better basis.
- Only a tariff rule that scales billing demand to a power-factor threshold is priced here; kVA billing and per-kVAR charges are priced in the workbench's bill.
- Harmonics, resonance, and switching transients are not assessed.