Interconnection queue in Wyoming
Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.
This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.
LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.
Statewide
- Active capacity
- 16,175 MW
- Active requests
- 73
- Median years in queue (active)
- 2.6
- Withdrawn, of requests entered by 2020
- 78%
| Type | Active capacity (MW) | Projects |
|---|---|---|
| Solar | 1,503 | 7 |
| Wind | 5,165 | 30 |
| Storage | 929 | 5 |
| Gas | 2,463 | 10 |
| Hybrid | 5,116 | 19 |
| Other | 1,000 | 2 |
By county
| County | Active capacity (MW) | Projects | Solar | Wind | Storage | Gas | Hybrid | Other | Median years in queue (active) | Withdrawn, of requests entered by 2020 |
|---|---|---|---|---|---|---|---|---|---|---|
| Laramie | 4,387 | 19 | 1,350 | 79 | 615 | 2,343 | 1.6 | |||
| Carbon | 2,662 | 16 | 851 | 1,481 | 330 | 3.7 | 82% of 61 | |||
| Converse | 2,275 | 10 | 492 | 234 | 750 | 600 | 199 | 2.3 | 73% of 26 | |
| Platte | 2,110 | 8 | 160 | 450 | 1,500 | 2.6 | ||||
| Lincoln | 1,848 | 5 | 800 | 48 | 1,000 | 3.6 | ||||
| Sweetwater | 1,200 | 2 | 1,200 | 0.3 | 82% of 33 | |||||
| Campbell | 590 | 3 | 590 | 3.8 | ||||||
| Natrona | 409 | 4 | 100 | 309 | 5.7 | |||||
| Goshen | 200 | 1 | 200 | 0.4 | ||||||
| Albany | 160 | 1 | 160 | 0.3 | ||||||
| Fort Bridger | 140 | 2 | 140 | 2.1 | ||||||
| Uinta | 120 | 1 | 120 | 10.2 | ||||||
| Fremont | 75 | 1 | 75 | 9.4 | ||||||
| Sublette | 0 | 0 | ||||||||
| Big Horn | 0 | 0 | ||||||||
| Jackson | 0 | 0 | ||||||||
| Rock Springs | 0 | 0 | ||||||||
| Carbon/Albany | 0 | 0 | ||||||||
| Park | 0 | 0 | ||||||||
| Johnson | 0 | 0 | ||||||||
| Washakie | 0 | 0 |
Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.
Active requests
Status is as of Dec 31, 2025. Current status at Interconnection.fyi.
| Project | County | Type | MW | Entered the queue | Study phase | Utility or operator | Live status |
|---|---|---|---|---|---|---|---|
| GI-CS-2025-25 | Platte | Solar+Battery | 800 | 2025-10-02 | Cluster Study | Tri-State Generation and Transmission Association | Current status |
| 37316 | Laramie | Gas+Battery+Other Storage | 600 | 2025-07-29 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| T2-033 | Sweetwater | Gas | 600 | 2025-09-05 | PacifiCorp | Current status | |
| T2-034 | Sweetwater | Gas | 600 | 2025-09-05 | PacifiCorp | Current status | |
| T2-017 | Converse | Gas | 600 | 2025-08-29 | PacifiCorp | Current status | |
| C1-35 | Carbon | Wind | 500 | 2021-05-13 | IA Executed | PacifiCorp | Current status |
| C2-32 | Lincoln | Nuclear | 500 | 2022-04-26 | IA Executed | PacifiCorp | Current status |
| S0039 | Lincoln | Nuclear | 500 | 2025-11-04 | In Progress (unknown study) | PacifiCorp | Current status |
| CLPT G21 | Laramie | Solar+Battery | 400 | 2022-09-06 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 836 | Carbon | Wind | 400 | 2016-12-05 | IA Executed | PacifiCorp | Current status |
| C2-106 | Lincoln | Wind | 400 | 2022-05-13 | Facility Study | PacifiCorp | Current status |
| PIS089 | Lincoln | Wind | 400 | 2024-10-31 | In Progress (unknown study) | PacifiCorp | Current status |
| T2-057 | Carbon | Wind | 400 | 2025-09-12 | PacifiCorp | Current status | |
| GI-TC-2024-16 | Laramie | Wind | 400 | 2023-05-16 | IA Executed | Tri-State Generation and Transmission Association | Current status |
| CLPT G20 | Laramie | Solar+Battery | 365 | 2022-07-20 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| S0026 | Converse | Battery | 350 | 2024-02-08 | In Progress (unknown study) | PacifiCorp | Current status |
| 21-08242 | Laramie | Wind | 350 | 2021-08-24 | System Impact Study | Platte River Power Authority | Current status |
| T2-051 | Carbon | Solar+Battery | 330 | 2025-09-11 | PacifiCorp | Current status | |
| GI-CS-2025-04 | Laramie | Wind+Battery | 330 | 2025-09-17 | Cluster Study | Tri-State Generation and Transmission Association | Current status |
| S0028 | Converse | Battery | 320 | 2024-02-08 | In Progress (unknown study) | PacifiCorp | Current status |
| CLPT G16 | Platte | Solar+Wind+Battery | 300 | 2022-04-01 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| CLPT G17 | Laramie | Solar+Wind+Battery | 300 | 2022-04-01 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| BHBE G16 | Campbell | Wind | 290 | 2021-12-14 | IA Executed | Black Hills Power | Current status |
| CLPT G18 | Converse | Solar | 255 | 2022-06-24 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| S0005 | Carbon | Solar | 250 | 2022-03-07 | In Progress (unknown study) | PacifiCorp | Current status |
| S0006 | Carbon | Solar | 250 | 2022-03-07 | In Progress (unknown study) | PacifiCorp | Current status |
| GI-TC-2024-15 | Laramie | Wind | 250 | 2024-05-23 | IA Executed | Tri-State Generation and Transmission Association | Current status |
| S0004 | Carbon | Solar | 240 | 2022-03-07 | In Progress (unknown study) | PacifiCorp | Current status |
| S0003 | Converse | Solar | 237 | 2022-03-07 | In Progress (unknown study) | PacifiCorp | Current status |
| CLPT G24 | Laramie | Wind | 200 | 2023-02-20 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 37681 | Platte | Solar+Wind+Battery | 200 | 2025-07-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 38047 | Platte | Solar+Wind+Battery | 200 | 2025-07-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 38412 | Goshen | Solar+Wind+Battery | 200 | 2025-07-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| BHBE G17 | Campbell | Wind | 200 | 2022-03-22 | IA Executed | Black Hills Power | Current status |
| C3-038 | Converse | Solar+Battery | 199 | 2023-05-08 | PacifiCorp | Current status | |
| T2-069 | Natrona | Solar+Battery | 199 | 2025-09-12 | PacifiCorp | Current status | |
| 39873 | Laramie | Wind+Battery | 198 | 2025-08-01 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| T2-026 | Albany | Solar+Battery | 160 | 2025-09-04 | PacifiCorp | Current status | |
| GI-TC-2024-03 | Platte | Solar | 160 | 2023-05-08 | In Progress (unknown study) | Tri-State Generation and Transmission Association | Current status |
| CLPT G23 | Laramie | Wind | 150 | 2023-02-20 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| CLPT G29 | Laramie | Solar+Wind+Battery | 150 | 2024-05-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| C2-49 | Converse | Wind | 150 | 2022-05-05 | Facility Study | PacifiCorp | Current status |
| GI-TC-2024-04 | Platte | Wind | 150 | 2023-05-22 | In Progress (unknown study) | Tri-State Generation and Transmission Association | Current status |
| GI-TC-2024-05 | Platte | Wind | 150 | 2023-05-22 | In Progress (unknown study) | Tri-State Generation and Transmission Association | Current status |
| GI-TC-2024-06 | Platte | Wind | 150 | 2023-05-22 | In Progress (unknown study) | Tri-State Generation and Transmission Association | Current status |
| 715 | Uinta | Wind | 120 | 2015-10-29 | IA Executed | PacifiCorp | Current status |
| CLPT G22 | Laramie | Gas | 115 | 2022-11-23 | IA Executed | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| CLPT G30 | Laramie | Gas | 115 | 2024-05-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| CLPT G31 | Laramie | Gas | 115 | 2024-05-30 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 40603 | Laramie | Gas | 115 | 2025-08-11 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 40969 | Laramie | Gas | 115 | 2025-08-11 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| S0002 | Carbon | Solar | 111 | 2022-03-07 | In Progress (unknown study) | PacifiCorp | Current status |
| BHBE G18 | Campbell | Wind | 100 | 2022-03-22 | IA Executed | Black Hills Power | Current status |
| S0025 | Natrona | Battery | 100 | 2024-02-08 | In Progress (unknown study) | PacifiCorp | Current status |
| 784 | Natrona | Solar+Battery | 80 | 2016-08-04 | IA Executed | PacifiCorp | Current status |
| S0038 | Converse | Battery | 80 | 2025-06-02 | In Progress (unknown study) | PacifiCorp | Current status |
| S0024 | Fort Bridger | Wind | 80 | 2023-11-20 | In Progress (unknown study) | PacifiCorp | Current status |
| 39508 | Laramie | Battery | 79 | 2025-08-01 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 789 | Fremont | Solar+Battery | 75 | 2016-08-08 | IA Executed | PacifiCorp | Current status |
| S0023 | Fort Bridger | Wind | 60 | 2023-11-20 | In Progress (unknown study) | PacifiCorp | Current status |
| C2-48 | Lincoln | Gas | 48 | 2022-05-03 | IA Executed | PacifiCorp | Current status |
| C2-12 | Converse | Wind | 42 | 2022-04-06 | IA Executed | PacifiCorp | Current status |
| PIS051 | Converse | Wind | 42 | 2024-02-22 | In Progress (unknown study) | PacifiCorp | Current status |
| 38777 | Laramie | Gas | 40 | 2025-07-31 | Cluster Study | Black Hills Cheyenne Light Fuel and Power Transmission | Current status |
| 783 | Natrona | Solar+Battery | 30 | 2016-08-03 | IA Executed | PacifiCorp | Current status |
| C2-13 | Carbon | Wind | 30 | 2022-04-06 | IA Executed | PacifiCorp | Current status |
| PIS052 | Carbon | Wind | 30 | 2024-02-22 | In Progress (unknown study) | PacifiCorp | Current status |
| C2-14 | Carbon | Wind | 28 | 2022-04-06 | IA Executed | PacifiCorp | Current status |
| PIS053 | Carbon | Wind | 28 | 2024-02-22 | In Progress (unknown study) | PacifiCorp | Current status |
| C2-11 | Carbon | Wind | 26 | 2022-04-06 | IA Executed | PacifiCorp | Current status |
| PIS050 | Carbon | Wind | 26 | 2024-02-22 | In Progress (unknown study) | PacifiCorp | Current status |
| C2-15 | Carbon | Wind | 7 | 2022-04-06 | IA Executed | PacifiCorp | Current status |
| PIS054 | Carbon | Wind | 7 | 2024-02-22 | In Progress (unknown study) | PacifiCorp | Current status |
Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by May 7, 2027. Last checked for an update: Oct 31, 2026.