Interconnection queue

Interconnection queue in Tennessee

Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.

This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.

LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.

Statewide

Active capacity
13,802 MW
Active requests
53
Median years in queue (active)
2.7
Withdrawn, of requests entered by 2020
77%
Active capacity by type
TypeActive capacity (MW)Projects
Solar1,41613
Storage7476
Gas10,66515
Hybrid6995
Other27514

By county

Queue requests by county in Tennessee, as of Dec 31, 2025
CountyActive capacity (MW)ProjectsSolarWindStorageGasHybridOtherMedian years in queue (active)Withdrawn, of requests entered by 2020
Stewart2,40022,4002.9
Trousdale2,40022,4001.6
Roane1,83931001,689502.7
Shelby1,78173001,407748.281% of 31
Haywood1,1943671,1271.685% of 20
Humphreys95039505.7
Fayette83921476924.8
Hawkins32522251001.5
Henderson27522753.8
Hardeman25012500.4
Moore20012005.5
Lawrence19511956.6
Lake17731779.4
Mcnairy1622621000.4
Bledsoe15011503.6
Carroll14011403.4
Cumberland11011104.2
Hamilton10351031.4
Maury10011001.8
Marion835838.4
Mcminn681680.5
Grainger321321.3
Loudon2932271.2
Sullivan00
Greene00
Hardin00
Sumner00
Weakley00
Cheatham00
Franklin00
Montgomery00
Gibson00
Robertson00
Anderson00
Campbell00
Hickman00
Johnson00
Wilson00
Davidson00
Madison00
Rhea00
Warren00
Grundy00
Morgan00
Tipton00
Carter00
Crockett00
Polk00
Henry00
Benton00
Lincoln00
Obion00
Coffee00
Putnam00
Cocke00
Bedford00
Van Buren00
Jefferson00
Overton00
Marshall00
Dekalb00
Dickson00
Dryer/Gibson00
Dyer00
Wayne00
Knox00

Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.

Active requests

Status is as of Dec 31, 2025. Current status at Interconnection.fyi.

Active interconnection requests in Tennessee
ProjectCountyTypeMWEntered the queueStudy phaseUtility or operatorLive status
489RoaneGas1,6892021-12-09Facility StudyTennessee Valley AuthorityCurrent status
483StewartGas1,6002021-10-08Facility StudyTennessee Valley AuthorityCurrent status
620TrousdaleGas1,6002024-06-12Cluster StudyTennessee Valley AuthorityCurrent status
257ShelbyGas1,1322014-08-22IA ExecutedTennessee Valley AuthorityCurrent status
618StewartGas8002024-06-12Facility StudyTennessee Valley AuthorityCurrent status
622TrousdaleGas8002024-06-12Cluster StudyTennessee Valley AuthorityCurrent status
25RSC-012HaywoodGas7522025-08-14In Progress (unknown study)Tennessee Valley AuthorityCurrent status
25RSC-001FayetteGas6922025-07-03In Progress (unknown study)Tennessee Valley AuthorityCurrent status
401HumphreysGas5932019-09-11IA ExecutedTennessee Valley AuthorityCurrent status
624HaywoodGas3752024-06-12Facility StudyTennessee Valley AuthorityCurrent status
636HumphreysGas2762024-07-05Cluster StudyTennessee Valley AuthorityCurrent status
25RSC-009HardemanSolar+Battery2502025-08-01In Progress (unknown study)Tennessee Valley AuthorityCurrent status
588ShelbyGas2382023-11-03Facility StudyTennessee Valley AuthorityCurrent status
587HawkinsBattery2252023-10-11Facility StudyTennessee Valley AuthorityCurrent status
445MooreSolar2002020-06-22IA ExecutedTennessee Valley AuthorityCurrent status
661ShelbyBattery2002024-10-01Cluster StudyTennessee Valley AuthorityCurrent status
374LawrenceSolar1952019-06-04IA ExecutedTennessee Valley AuthorityCurrent status
501BledsoeSolar1502022-05-23IA ExecutedTennessee Valley AuthorityCurrent status
538HendersonSolar+Battery1502023-03-28IA ExecutedTennessee Valley AuthorityCurrent status
305FayetteSolar1472016-11-22IA ExecutedTennessee Valley AuthorityCurrent status
510CarrollSolar1402022-07-22IA ExecutedTennessee Valley AuthorityCurrent status
469HendersonSolar+Battery1252021-03-23IA ExecutedTennessee Valley AuthorityCurrent status
482CumberlandSolar1102021-10-05IA ExecutedTennessee Valley AuthorityCurrent status
AH1-535HawkinsSolar+Battery1002025-03-06System Impact StudyAEPCurrent status
25RSC-007McnairyBattery1002025-07-29In Progress (unknown study)Tennessee Valley AuthorityCurrent status
547RoaneBattery1002023-04-17Facility StudyTennessee Valley AuthorityCurrent status
611MaurySolar1002024-03-25Facility StudyTennessee Valley AuthorityCurrent status
643ShelbyBattery1002024-09-06Cluster StudyTennessee Valley AuthorityCurrent status
426HumphreysGas812020-04-23IA ExecutedTennessee Valley AuthorityCurrent status
292LakeSolar802016-04-19IA ExecutedTennessee Valley AuthorityCurrent status
333ShelbySolar+Battery742017-10-18IA ExecutedTennessee Valley AuthorityCurrent status
25RSC-003McminnSolar682025-07-10In Progress (unknown study)Tennessee Valley AuthorityCurrent status
299LakeSolar672016-07-28IA ExecutedTennessee Valley AuthorityCurrent status
515HaywoodSolar672022-08-25IA ExecutedTennessee Valley AuthorityCurrent status
25RSC-006McnairySolar622025-07-29In Progress (unknown study)Tennessee Valley AuthorityCurrent status
25RSC-002RoaneNuclear502025-07-01In Progress (unknown study)Tennessee Valley AuthorityCurrent status
648GraingerHydro322024-09-20Cluster StudyTennessee Valley AuthorityCurrent status
337LakeSolar302018-01-02IA ExecutedTennessee Valley AuthorityCurrent status
322MarionHydro272017-08-04IA ExecutedTennessee Valley AuthorityCurrent status
323MarionHydro272017-08-04IA ExecutedTennessee Valley AuthorityCurrent status
627HamiltonNuclear252024-06-12Cluster StudyTennessee Valley AuthorityCurrent status
637HamiltonNuclear242024-08-14Cluster StudyTennessee Valley AuthorityCurrent status
654HamiltonHydro242024-09-26Cluster StudyTennessee Valley AuthorityCurrent status
655HamiltonHydro242024-09-26Cluster StudyTennessee Valley AuthorityCurrent status
332ShelbyGas232017-10-18IA ExecutedTennessee Valley AuthorityCurrent status
461LoudonBattery222020-11-04IA ExecutedTennessee Valley AuthorityCurrent status
304ShelbyGas142016-11-21IA ExecutedTennessee Valley AuthorityCurrent status
320MarionHydro112017-08-04IA ExecutedTennessee Valley AuthorityCurrent status
321MarionHydro112017-08-04IA ExecutedTennessee Valley AuthorityCurrent status
590MarionHydro72023-11-03Cluster StudyTennessee Valley AuthorityCurrent status
471HamiltonNuclear62021-03-30IA ExecutedTennessee Valley AuthorityCurrent status
659LoudonHydro42024-10-01Cluster StudyTennessee Valley AuthorityCurrent status
658LoudonHydro32024-10-01Cluster StudyTennessee Valley AuthorityCurrent status

Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent