Interconnection queue in South Dakota
Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.
This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.
LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.
Statewide
- Active capacity
- 9,628 MW
- Active requests
- 48
- Median years in queue (active)
- 3.2
- Withdrawn, of requests entered by 2020
- 74%
| Type | Active capacity (MW) | Projects |
|---|---|---|
| Solar | 2,140 | 11 |
| Wind | 2,902 | 16 |
| Storage | 700 | 3 |
| Gas | 1,669 | 7 |
| Hybrid | 810 | 4 |
| Other | 1,407 | 7 |
By county
| County | Active capacity (MW) | Projects | Solar | Wind | Storage | Gas | Hybrid | Other | Median years in queue (active) | Withdrawn, of requests entered by 2020 |
|---|---|---|---|---|---|---|---|---|---|---|
| Campbell | 2,064 | 10 | 300 | 499 | 1,265 | 19.4 | ||||
| Deuel | 1,536 | 3 | 250 | 1,144 | 142 | 1.8 | ||||
| Brookings | 1,245 | 3 | 980 | 265 | 0.7 | |||||
| Brown | 512 | 4 | 99 | 143 | 270 | 1.5 | ||||
| Grant | 500 | 2 | 500 | 0.2 | 86% of 28 | |||||
| Clark | 450 | 2 | 450 | 8.9 | ||||||
| Codington | 440 | 3 | 200 | 240 | 2.2 | 83% of 24 | ||||
| Meade | 400 | 4 | 400 | 2.0 | ||||||
| Mcpherson | 400 | 2 | 400 | 1.8 | ||||||
| Day | 300 | 1 | 300 | 1.7 | ||||||
| Haakon | 300 | 1 | 300 | 8.6 | ||||||
| Turner | 270 | 1 | 270 | 8.1 | ||||||
| Dawes | 250 | 1 | 250 | 3.4 | ||||||
| Roberts | 200 | 1 | 200 | 3.3 | ||||||
| Bon Homme | 200 | 1 | 200 | 10.9 | ||||||
| Lincoln | 120 | 1 | 120 | 1.7 | ||||||
| Pennington | 115 | 1 | 115 | 1.5 | ||||||
| Oglala Lakota | 110 | 1 | 110 | 3.1 | ||||||
| Butte | 103 | 1 | 103 | 12.0 | ||||||
| Mccook | 100 | 2 | 100 | 7.2 | ||||||
| Aurora | 11 | 1 | 11 | 0.2 | ||||||
| Beadle | 3 | 2 | 3 | 1.6 | ||||||
| Shannon | 0 | 0 | ||||||||
| Custer | 0 | 0 | ||||||||
| Lawrence | 0 | 0 | ||||||||
| Weston | 0 | 0 | ||||||||
| Edmunds | 0 | 0 | ||||||||
| Minnehaha | 0 | 0 | ||||||||
| Marshall | 0 | 0 | ||||||||
| Corson | 0 | 0 | ||||||||
| Hand | 0 | 0 | ||||||||
| Jerauld | 0 | 0 | ||||||||
| Moody | 0 | 0 | ||||||||
| County not given | 0 | 0 | ||||||||
| Walworth | 0 | 0 | ||||||||
| Brule | 0 | 0 | ||||||||
| Davison | 0 | 0 | ||||||||
| Spink | 0 | 0 | ||||||||
| Todd | 0 | 0 | ||||||||
| Hyde | 0 | 0 | ||||||||
| Perkins | 0 | 0 | ||||||||
| Bennett | 0 | 0 | ||||||||
| Dewey | 0 | 0 | ||||||||
| Yankton | 0 | 0 | ||||||||
| Sully | 0 | 0 | ||||||||
| Tripp | 0 | 0 | ||||||||
| Potter | 0 | 0 | ||||||||
| Union | 0 | 0 | ||||||||
| Buffalo | 0 | 0 | ||||||||
| Kingsbury | 0 | 0 | ||||||||
| Stanley | 0 | 0 | ||||||||
| Charles Mix | 0 | 0 | ||||||||
| Clay | 0 | 0 | ||||||||
| Gregory | 0 | 0 | ||||||||
| Hanson | 0 | 0 | ||||||||
| Lyman | 0 | 0 | ||||||||
| Hughes | 0 | 0 |
Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.
Active requests
Status is as of Dec 31, 2025. Current status at Interconnection.fyi.
| Project | County | Type | MW | Entered the queue | Study phase | Utility or operator | Live status |
|---|---|---|---|---|---|---|---|
| J3941 | Deuel | Gas | 1,144 | 2025-03-26 | OTTER TAIL POWER COMPANY | Current status | |
| J3963 | Brookings | Solar | 490 | 2025-04-07 | NORTHERN STATES POWER COMPANY | Current status | |
| J3964 | Brookings | Solar | 490 | 2025-04-07 | NORTHERN STATES POWER COMPANY | Current status | |
| BHBE G11 | Campbell | Coal | 475 | 2011-09-26 | IA Executed | Black Hills Power | Current status |
| BHBE G19 | Campbell | Solar | 300 | 2022-05-03 | IA Executed | Black Hills Power | Current status |
| BHBE G4 | Campbell | Coal | 300 | 2005-01-07 | IA Executed | Black Hills Power | Current status |
| J3468 | Day | Wind+Battery | 300 | 2024-04-12 | In Progress (unknown study) | OTTER TAIL POWER COMPANY | Current status |
| GEN-2017-014 | Haakon | Wind | 300 | 2017-05-22 | IA Executed | WAPA | Current status |
| GEN-2017-175 | Turner | Wind | 270 | 2017-11-29 | IA Executed | WAPA | Current status |
| GEN-2024-035 | Brown | Solar+Battery | 270 | 2024-10-30 | System Impact Study | BEPC | Current status |
| E0034 | Brookings | Gas | 265 | 2025-08-12 | In Progress (unknown study) | Basin Electric Power Cooperative | Current status |
| BHBE G1 | Campbell | Coal | 250 | 2001-02-06 | IA Executed | Black Hills Power | Current status |
| BHBE G20 | Dawes | Solar | 250 | 2022-07-25 | IA Executed | Black Hills Power | Current status |
| J1485 | Deuel | Wind | 250 | 2019-04-29 | IA Pending | OTTER TAIL POWER COMPANY | Current status |
| J4081 | Grant | Battery | 250 | 2025-10-07 | OTTER TAIL POWER COMPANY | Current status | |
| J4153 | Grant | Battery | 250 | 2025-10-07 | OTTER TAIL POWER COMPANY | Current status | |
| GEN-2024-285 | Clark | Wind | 250 | 2025-03-01 | System Impact Study | BEPC | Current status |
| BHBE G21 | Campbell | Wind | 200 | 2022-08-23 | IA Executed | Black Hills Power | Current status |
| BHBE G7 | Campbell | Wind | 200 | 2007-10-01 | IA Executed | Black Hills Power | Current status |
| J2852 | Roberts | Battery | 200 | 2022-09-14 | Cluster Study | OTTER TAIL POWER COMPANY | Current status |
| J3420 | Mcpherson | Wind | 200 | 2024-03-18 | In Progress (unknown study) | OTTER TAIL POWER COMPANY | Current status |
| J3428 | Mcpherson | Wind | 200 | 2024-03-18 | In Progress (unknown study) | OTTER TAIL POWER COMPANY | Current status |
| J722 | Codington | Wind | 200 | 2017-06-16 | Construction | OTTER TAIL POWER COMPANY | Current status |
| GI-0901 | Clark | Wind | 200 | 2009-01-22 | IA Executed | WAPA/BEPC/HCPD Integrated System | Current status |
| GI-1501 | Bon Homme | Wind | 200 | 2015-02-24 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| GEN-2024-282 | Meade | Solar | 150 | 2025-03-01 | System Impact Study | WAPA | Current status |
| GEN-2024-283 | Meade | Solar | 150 | 2025-03-01 | System Impact Study | WAPA | Current status |
| J3400 | Deuel | Other | 142 | 2024-03-20 | In Progress (unknown study) | OTTER TAIL POWER COMPANY | Current status |
| ERAS-2025-035 | Brown | Gas | 138 | 2025-10-02 | In Progress (unknown study) | NWPS | Current status |
| J3546 | Lincoln | Wind | 120 | 2024-04-18 | In Progress (unknown study) | NORTHERN STATES POWER COMPANY | Current status |
| Surplus; G736 | Codington | Other+Battery | 120 | 2023-10-13 | OTTER TAIL POWER COMPANY | Current status | |
| Surplus; J442 | Codington | Other+Battery | 120 | 2023-10-13 | OTTER TAIL POWER COMPANY | Current status | |
| BHBE G25 | Pennington | Gas | 115 | 2024-06-13 | Cluster Study | Black Hills Power | Current status |
| BHBE G23 | Oglala Lakota | Solar | 110 | 2022-11-08 | IA Executed | Black Hills Power | Current status |
| GI-1401 | Butte | Wind | 103 | 2014-01-06 | IA Executed | WAPA/BEPC/HCPD Integrated System | Current status |
| BHBE G2 | Campbell | Coal | 100 | 2001-02-27 | IA Executed | Black Hills Power | Current status |
| BHBE G5 | Campbell | Coal | 100 | 2005-05-23 | IA Executed | Black Hills Power | Current status |
| GI-1505 | Brown | Wind | 99 | 2015-04-08 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| GEN-2016-087 | Campbell | Wind | 99 | 2016-07-25 | IA Executed | WAPA | Current status |
| BHBE G15 | Meade | Solar | 80 | 2021-05-11 | IA Executed | Black Hills Power | Current status |
| J1169 | Mccook | Solar | 50 | 2018-03-12 | IA Executed | NORTHERN STATES POWER COMPANY | Current status |
| J1312 | Mccook | Solar | 50 | 2019-04-29 | IA Executed | NORTHERN STATES POWER COMPANY | Current status |
| BHBE G3 | Campbell | Coal | 40 | 2004-08-25 | IA Executed | Black Hills Power | Current status |
| BHBE G22 | Meade | Solar | 20 | 2022-10-05 | IA Executed | Black Hills Power | Current status |
| GEN-2025-GR4 | Aurora | Wind | 11 | 2025-10-06 | In Progress (unknown study) | WAPA | Current status |
| 456 | Brown | Gas | 5 | 2024-02-02 | NorthWestern Energy | Current status | |
| 462 | Beadle | Gas | 2 | 2024-06-05 | NorthWestern Energy | Current status | |
| 463 | Beadle | Gas | 1 | 2024-06-05 | NorthWestern Energy | Current status |
Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by May 7, 2027. Last checked for an update: Oct 31, 2026.