Interconnection queue in New Jersey

Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.

This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.

LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.

Statewide

Active capacity
14,544 MW
Active requests
66
Median years in queue (active)
3.8
Withdrawn, of requests entered by 2020
76%
Active capacity by type
TypeActive capacity (MW)Projects
Solar60027
Wind9,5116
Storage3,65926
Gas4104
Hybrid1082
Other2571

By county

Queue requests by county in New Jersey, as of Dec 31, 2025
CountyActive capacity (MW)ProjectsSolarWindStorageGasHybridOtherMedian years in queue (active)Withdrawn, of requests entered by 2020
Monmouth5,2877354,7525002.974% of 54
Atlantic2,74762,139570384.178% of 72
Middlesex2,62022,6203.373% of 92
Salem8545655322570.886% of 95
Camden60026002.479% of 39
Warren4371132740703.379% of 85
Hudson35023506.063% of 40
Gloucester3215183045.378% of 68
Union30723070.758% of 33
Hunterdon3002202804.374% of 73
Ocean2497791702.968% of 37
Mercer17011706.372% of 25
Cumberland106426805.084% of 77
Bergen10221025.255% of 29
Sussex2626204.881% of 59
Burlington232234.672% of 109
Cape May201206.188% of 33
Morris151155.386% of 21
Somerset8183.7
County not given2123.9
Essex0061% of 28
Passaic00

Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.

Active requests

Status is as of Dec 31, 2025. Current status at Interconnection.fyi.

Active interconnection requests in New Jersey
ProjectCountyTypeMWEntered the queueStudy phaseUtility or operatorLive status
AI2-431AtlanticOffshore Wind2,1392023-03-10Feasibility StudyJCPLCurrent status
AI1-001MonmouthOffshore Wind2,1002022-04-02Feasibility StudyJCPLCurrent status
AJ1-015MonmouthOffshore Wind1,3422023-06-02Feasibility StudyJCPLCurrent status
AI1-109MiddlesexOffshore Wind1,3102022-09-01Feasibility StudyPSEGCurrent status
AI1-110MonmouthOffshore Wind1,3102022-09-01Feasibility StudyJCPLCurrent status
AI1-111MiddlesexOffshore Wind1,3102022-09-01Feasibility StudyJCPLCurrent status
AH2-333SalemBattery4152022-03-11Feasibility StudyAECCurrent status
AH1-260CamdenBattery3002025-01-27System Impact StudyAECCurrent status
AH2-334CamdenBattery3002022-03-10Feasibility StudyPSEGCurrent status
AI1-187HunterdonBattery2802022-09-09Feasibility StudyJCPLCurrent status
AH1-710SalemNuclear2572025-04-09System Impact StudyPSEGCurrent status
Woods Landing Energy StorageAtlanticBattery2502020-03-31IA ExecutedJCPLCurrent status
AI2-068MonmouthBattery2502023-02-24Feasibility StudyJCPLCurrent status
AI2-069MonmouthBattery2502023-02-24Feasibility StudyJCPLCurrent status
Hudson Energy Storage FacilityHudsonBattery2002019-09-30IA ExecutedPSEGCurrent status
AH2-378AGloucesterBattery2002022-03-10Feasibility StudyAECCurrent status
Lamberton Road BatteryMercerBattery1702019-09-28IA ExecutedPSEGCurrent status
AH1-722UnionGas1582025-04-08System Impact StudyPSEGCurrent status
AI1-137WarrenSolar1552022-09-09Feasibility StudyJCPLCurrent status
Two Rivers StorageHudsonBattery1502020-03-31IA ExecutedPSEGCurrent status
AI2-070AtlanticBattery1502023-02-24Feasibility StudyAECCurrent status
AI2-071AtlanticBattery1502023-02-24Feasibility StudyAECCurrent status
AH1-715UnionGas1492025-04-08System Impact StudyPSEGCurrent status
AH2-132SalemBattery1172022-03-01Feasibility StudyAECCurrent status
AH2-131GloucesterBattery1042022-02-28Feasibility StudyAECCurrent status
AH2-269OceanBattery1002022-03-10Feasibility StudyJCPLCurrent status
Harmony Plains Solar and Storage FacilityWarrenSolar+Battery702019-10-01IA ExecutedJCPLCurrent status
AI2-052OceanBattery702023-02-17Feasibility StudyJCPLCurrent status
AI1-120WarrenSolar522022-09-07Feasibility StudyJCPLCurrent status
AH1-703BergenGas512025-04-08System Impact StudyPSEGCurrent status
Bergen Generating StationBergenGas512016-04-26IA ExecutedPSEGCurrent status
South OrchardCumberlandBattery502019-09-28IA ExecutedAECCurrent status
AG2-616SalemSolar502025-03-11System Impact StudyAECCurrent status
Fenwick Creek SolarAtlanticSolar+Battery382020-09-25IA ExecutedAECCurrent status
AI1-118WarrenSolar382022-09-06Feasibility StudyJCPLCurrent status
South OrchardCumberlandBattery302019-09-28IA ExecutedAECCurrent status
Warren Glen StorageWarrenBattery202018-09-29IA ExecutedJCPLCurrent status
Houses Corner StorageSussexBattery202019-09-30IA ExecutedJCPLCurrent status
Mansfield #3WarrenBattery202019-09-30IA ExecutedJCPLCurrent status
Middle Battery StorageCape MayBattery202019-11-15IA ExecutedAECCurrent status
Missouri Avenue Battery Storage ProjectAtlanticBattery202019-11-15IA ExecutedAECCurrent status
AI2-437WarrenSolar202023-03-10Feasibility StudyJCPLCurrent status
Lacey Sand SolarOceanSolar202020-09-17IA ExecutedJCPLCurrent status
Ridge Road Solar FarmHunterdonSolar202020-09-30IA ExecutedJCPLCurrent status
AG2-016OceanSolar202025-03-10System Impact StudyJCPLCurrent status
AG2-625WarrenSolar202025-02-12System Impact StudyJCPLCurrent status
Kober Solar FarmWarrenSolar192025-02-20System Impact StudyJCPLCurrent status
Port Belford Solar FarmMonmouthSolar192025-01-31System Impact StudyJCPLCurrent status
Heritage Solar FarmOceanSolar192025-03-14System Impact StudyJCPLCurrent status
AG2-297CumberlandSolar192025-02-28System Impact StudyAECCurrent status
AH2-127BurlingtonBattery182022-02-25Feasibility StudyPSEGCurrent status
South CombeMorrisSolar152020-09-17IA ExecutedJCPLCurrent status
Monmouth Solar 1MonmouthSolar152020-09-23IA ExecutedJCPLCurrent status
AH1-641SalemSolar152025-03-11System Impact StudyAECCurrent status
AG2-626WarrenSolar132025-02-12System Impact StudyJCPLCurrent status
Southern Ocean Waretown SolarOceanSolar122020-09-17IA ExecutedJCPLCurrent status
Washington Solar PH IIWarrenSolar112020-03-31IA ExecutedJCPLCurrent status
Esky Solar ProjectGloucesterSolar102020-09-30IA ExecutedAECCurrent status
AH1-054OceanSolar82025-02-03System Impact StudyJCPLCurrent status
AI1-033SomersetSolar82022-04-05Feasibility StudyPSEGCurrent status
AH2-412CumberlandSolar72022-03-10Feasibility StudyAECCurrent status
National Park NJGloucesterSolar62016-06-22IA ExecutedPSEGCurrent status
AI1-122SussexSolar62022-09-07Feasibility StudyJCPLCurrent status
NAESBurlingtonBattery52020-09-01IA ExecutedPSEGCurrent status
Monroe-Sicklerville Road LF SolarGloucesterSolar22018-03-23IA ExecutedAECCurrent status
AH2-109Solar22022-02-16Feasibility StudyAECCurrent status

Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0