Interconnection queue in North Dakota
Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.
This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.
LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.
Statewide
- Active capacity
- 14,500 MW
- Active requests
- 63
- Median years in queue (active)
- 3.2
- Withdrawn, of requests entered by 2020
- 73%
| Type | Active capacity (MW) | Projects |
|---|---|---|
| Solar | 1,531 | 10 |
| Wind | 5,448 | 27 |
| Storage | 2,139 | 12 |
| Gas | 3,241 | 6 |
| Hybrid | 1,275 | 4 |
| Other | 866 | 4 |
By county
| County | Active capacity (MW) | Projects | Solar | Wind | Storage | Gas | Hybrid | Other | Median years in queue (active) | Withdrawn, of requests entered by 2020 |
|---|---|---|---|---|---|---|---|---|---|---|
| Williams | 2,821 | 8 | 506 | 200 | 1,740 | 375 | 3.4 | |||
| Mercer | 2,445 | 6 | 349 | 596 | 1,500 | 0.8 | ||||
| Cass | 2,279 | 7 | 400 | 200 | 200 | 1,000 | 479 | 1.2 | 89% of 28 | |
| Morton | 1,010 | 6 | 907 | 103 | 3.8 | |||||
| Oliver | 702 | 3 | 702 | 6.7 | ||||||
| Stark | 657 | 4 | 332 | 325 | 5.5 | |||||
| Eddy | 610 | 3 | 401 | 209 | 6.7 | |||||
| Richland | 472 | 3 | 300 | 172 | 7.7 | |||||
| Grand Forks | 464 | 2 | 464 | 3.1 | ||||||
| Stutsman | 447 | 2 | 247 | 200 | 2.9 | |||||
| Ward | 408 | 4 | 208 | 200 | 4.5 | |||||
| Billings | 383 | 1 | 383 | 11.6 | ||||||
| Dickey | 300 | 1 | 300 | 1.7 | 83% of 24 | |||||
| Dunn | 300 | 1 | 300 | 0.8 | ||||||
| Sargent | 265 | 2 | 265 | 2.2 | ||||||
| Mcintosh | 262 | 2 | 250 | 12 | 16.0 | |||||
| Slope | 250 | 1 | 250 | 0.8 | ||||||
| Burke | 171 | 2 | 170 | 1 | 8.7 | |||||
| Mckenzie | 150 | 1 | 150 | 5.7 | ||||||
| Emmons | 85 | 2 | 85 | 0.2 | ||||||
| Lamoure | 20 | 1 | 20 | 1.6 | ||||||
| Mclean | 0 | 1 | 0 | 0.2 | ||||||
| Cavalier | 0 | 0 | ||||||||
| Barnes | 0 | 0 | ||||||||
| Pembina | 0 | 0 | ||||||||
| Burleigh | 0 | 0 | ||||||||
| Steele | 0 | 0 | ||||||||
| County not given | 0 | 0 | ||||||||
| Bowman | 0 | 0 | ||||||||
| Mchenry | 0 | 0 | ||||||||
| Pierce | 0 | 0 | ||||||||
| Rolette | 0 | 0 | ||||||||
| Mountrail | 0 | 0 | ||||||||
| Adams | 0 | 0 | ||||||||
| Sheridan | 0 | 0 | ||||||||
| Hettinger | 0 | 0 | ||||||||
| Grant | 0 | 0 | ||||||||
| Kidder | 0 | 0 | ||||||||
| Nelson | 0 | 0 | ||||||||
| Ramsey | 0 | 0 | ||||||||
| Logan | 0 | 0 | ||||||||
| Sioux | 0 | 0 | ||||||||
| Griggs | 0 | 0 | ||||||||
| Divide | 0 | 0 |
Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.
Active requests
Status is as of Dec 31, 2025. Current status at Interconnection.fyi.
| Project | County | Type | MW | Entered the queue | Study phase | Utility or operator | Live status |
|---|---|---|---|---|---|---|---|
| ERAS-2025-011 | Mercer | Gas | 750 | 2025-10-01 | In Progress (unknown study) | BEPC | Current status |
| ERAS-2025-012 | Mercer | Gas | 750 | 2025-10-01 | In Progress (unknown study) | BEPC | Current status |
| GEN-2024-081 | Williams | Gas | 745 | 2024-10-30 | System Impact Study | BEPC | Current status |
| GEN-2024-082 | Williams | Gas | 745 | 2024-10-30 | System Impact Study | BEPC | Current status |
| J4105 | Cass | Solar+Battery | 500 | 2025-10-06 | OTTER TAIL POWER COMPANY | Current status | |
| J4106 | Cass | Solar+Battery | 500 | 2025-10-06 | OTTER TAIL POWER COMPANY | Current status | |
| J3163 | Cass | Other | 479 | 2022-07-26 | Cluster Study | NORTHERN STATES POWER COMPANY | Current status |
| Red Butte Wind | Morton | Wind | 457 | 2025-08-06 | In Progress (unknown study) | Great River Energy (GRE) | Current status |
| GEN-2024-141 | Mercer | Wind | 424 | 2025-03-01 | System Impact Study | BEPC | Current status |
| GI-1404 | Billings | Wind | 383 | 2014-05-14 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| MPC04000 | Oliver | Wind | 300 | 2019-04-25 | IA Executed | Minnkota Power Cooperative | Current status |
| J3280 | Dickey | Wind | 300 | 2024-04-17 | In Progress (unknown study) | MONTANA-DAKOTA UTILITIES CO. | Current status |
| GEN-2024-331 | Dunn | Battery | 300 | 2025-03-01 | System Impact Study | BEPC | Current status |
| MPC04500 | Grand Forks | Wind | 258 | 2023-09-26 | Feasibility Study | Minnkota Power Cooperative | Current status |
| GEN-2018-067 | Williams | Wind | 255 | 2018-10-25 | IA Executed | MWEC | Current status |
| GI-1503 | Williams | Wind | 251 | 2015-03-23 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| MPC03800 | Eddy | Wind | 250 | 2019-02-21 | IA Executed | Minnkota Power Cooperative | Current status |
| J1040 | Mcintosh | Wind | 250 | 2018-03-12 | Construction | MONTANA-DAKOTA UTILITIES CO. | Current status |
| GEN-2022-010 | Williams | Other | 250 | 2022-05-26 | Facility Study | BEPC | Current status |
| GEN-2022-083 | Williams | Gas | 250 | 2022-10-21 | Facility Study | BEPC | Current status |
| GEN-2024-328 | Slope | Battery | 250 | 2025-03-01 | System Impact Study | BEPC | Current status |
| J3787 | Stutsman | Solar | 247 | 2024-04-16 | In Progress (unknown study) | OTTER TAIL POWER COMPANY | Current status |
| GEN-2024-326 | Stark | Battery | 225 | 2025-03-01 | System Impact Study | WAPA | Current status |
| MPC04600 | Eddy | Battery | 209 | 2025-11-25 | In Progress (unknown study) | Minnkota Power Cooperative | Current status |
| MPC04400 | Grand Forks | Wind | 206 | 2022-02-04 | System Impact Study | Minnkota Power Cooperative | Current status |
| GEN-2016-004 | Oliver | Wind | 202 | 2016-03-10 | IA Executed | BEPC | Current status |
| J1588 | Cass | Solar | 200 | 2024-04-30 | IA Pending | NORTHERN STATES POWER COMPANY | Current status |
| J2080 | Oliver | Wind | 200 | 2021-08-12 | Cluster Study | MINNESOTA POWER INC. | Current status |
| J2250 | Stutsman | Wind | 200 | 2021-11-01 | Cluster Study | MONTANA-DAKOTA UTILITIES CO. | Current status |
| J3522 | Cass | Solar | 200 | 2024-03-18 | In Progress (unknown study) | ITC MIDWEST | Current status |
| J3833 | Cass | Wind | 200 | 2024-10-01 | OTTER TAIL POWER COMPANY | Current status | |
| Surplus; J1588 | Cass | Battery | 200 | 2025-03-25 | NORTHERN STATES POWER COMPANY | Current status | |
| GEN-2024-327 | Ward | Battery | 200 | 2025-03-01 | System Impact Study | CPEC | Current status |
| GEN-2024-329 | Williams | Battery | 200 | 2025-03-01 | System Impact Study | MWEC | Current status |
| GEN-2024-284 | Mercer | Solar | 199 | 2025-03-01 | System Impact Study | BEPC | Current status |
| GI-1502 | Stark | Wind | 182 | 2015-03-23 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| GEN-2024-034 | Sargent | Battery | 175 | 2024-10-30 | System Impact Study | WAPA | Current status |
| J4170 | Richland | Solar+Battery | 172 | 2025-10-07 | OTTER TAIL POWER COMPANY | Current status | |
| GI-1508 | Mercer | Wind | 172 | 2015-09-30 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| MPC03600 | Richland | Solar | 170 | 2018-05-04 | IA Executed | Minnkota Power Cooperative | Current status |
| GEN-2023-SR4 | Burke | Battery | 170 | 2022-12-15 | IA Executed | BEPC | Current status |
| MPC03900 | Eddy | Wind | 151 | 2019-04-16 | IA Executed | Minnkota Power Cooperative | Current status |
| J2502 | Morton | Wind | 150 | 2022-09-13 | Cluster Study | MINNESOTA POWER INC. | Current status |
| GEN-2019-037 | Mercer | Solar | 150 | 2019-05-17 | IA Executed | BEPC | Current status |
| GEN-2020-091 | Mckenzie | Solar | 150 | 2020-04-30 | IA Executed | BEPC | Current status |
| GI-1509 | Stark | Wind | 150 | 2015-09-30 | In Progress (unknown study) | WAPA/BEPC/HCPD Integrated System | Current status |
| MPC03700 | Richland | Solar | 130 | 2018-05-04 | IA Executed | Minnkota Power Cooperative | Current status |
| GEN-2022-009 | Williams | Other | 125 | 2022-05-26 | Facility Study | BEPC | Current status |
| Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2 | Morton | Gas+Other | 103 | 2019-06-24 | MONTANA-DAKOTA UTILITIES CO. | Current status | |
| J2097 | Morton | Wind | 100 | 2021-08-25 | Cluster Study | MINNESOTA POWER INC. | Current status |
| J2157 | Morton | Wind | 100 | 2021-08-25 | Cluster Study | MINNESOTA POWER INC. | Current status |
| J3070 | Morton | Wind | 100 | 2022-09-15 | Cluster Study | MISO | Current status |
| GEN-2017-214 | Ward | Wind | 100 | 2017-11-30 | IA Executed | BEPC | Current status |
| GEN-2017-215 | Ward | Wind | 100 | 2017-11-30 | IA Executed | BEPC | Current status |
| GEN-2024-359 | Stark | Battery | 100 | 2025-03-01 | System Impact Study | WAPA | Current status |
| J2913 | Sargent | Battery | 90 | 2022-09-15 | Cluster Study | OTTER TAIL POWER COMPANY | Current status |
| J4077 | Emmons | Solar | 45 | 2025-10-06 | MONTANA-DAKOTA UTILITIES CO. | Current status | |
| J4070 | Emmons | Solar | 40 | 2025-10-07 | MONTANA-DAKOTA UTILITIES CO. | Current status | |
| GEN-2024-SR12 | Lamoure | Battery | 20 | 2024-05-21 | IA Pending | WAPA | Current status |
| G150 | Mcintosh | Other | 12 | 2001-11-13 | MISO | Current status | |
| GEN-2025-GR5 | Ward | Wind | 8 | 2025-10-06 | In Progress (unknown study) | WAPA | Current status |
| GI-1103 | Burke | Gas | 1 | 2011-09-09 | IA Executed | WAPA/BEPC/HCPD Integrated System | Current status |
| GEN-2025-GR3 | Mclean | Wind | 0 | 2025-10-06 | In Progress (unknown study) | WAPA | Current status |
Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by May 7, 2027. Last checked for an update: Oct 31, 2026.