Interconnection queue in North Dakota

Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.

This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.

LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.

Statewide

Active capacity
14,500 MW
Active requests
63
Median years in queue (active)
3.2
Withdrawn, of requests entered by 2020
73%
Active capacity by type
TypeActive capacity (MW)Projects
Solar1,53110
Wind5,44827
Storage2,13912
Gas3,2416
Hybrid1,2754
Other8664

By county

Queue requests by county in North Dakota, as of Dec 31, 2025
CountyActive capacity (MW)ProjectsSolarWindStorageGasHybridOtherMedian years in queue (active)Withdrawn, of requests entered by 2020
Williams2,82185062001,7403753.4
Mercer2,44563495961,5000.8
Cass2,27974002002001,0004791.289% of 28
Morton1,01069071033.8
Oliver70237026.7
Stark65743323255.5
Eddy61034012096.7
Richland47233001727.7
Grand Forks46424643.1
Stutsman44722472002.9
Ward40842082004.5
Billings383138311.6
Dickey30013001.783% of 24
Dunn30013000.8
Sargent26522652.2
Mcintosh26222501216.0
Slope25012500.8
Burke171217018.7
Mckenzie15011505.7
Emmons852850.2
Lamoure201201.6
Mclean0100.2
Cavalier00
Barnes00
Pembina00
Burleigh00
Steele00
County not given00
Bowman00
Mchenry00
Pierce00
Rolette00
Mountrail00
Adams00
Sheridan00
Hettinger00
Grant00
Kidder00
Nelson00
Ramsey00
Logan00
Sioux00
Griggs00
Divide00

Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.

Active requests

Status is as of Dec 31, 2025. Current status at Interconnection.fyi.

Active interconnection requests in North Dakota
ProjectCountyTypeMWEntered the queueStudy phaseUtility or operatorLive status
ERAS-2025-011MercerGas7502025-10-01In Progress (unknown study)BEPCCurrent status
ERAS-2025-012MercerGas7502025-10-01In Progress (unknown study)BEPCCurrent status
GEN-2024-081WilliamsGas7452024-10-30System Impact StudyBEPCCurrent status
GEN-2024-082WilliamsGas7452024-10-30System Impact StudyBEPCCurrent status
J4105CassSolar+Battery5002025-10-06OTTER TAIL POWER COMPANYCurrent status
J4106CassSolar+Battery5002025-10-06OTTER TAIL POWER COMPANYCurrent status
J3163CassOther4792022-07-26Cluster StudyNORTHERN STATES POWER COMPANYCurrent status
Red Butte WindMortonWind4572025-08-06In Progress (unknown study)Great River Energy (GRE)Current status
GEN-2024-141MercerWind4242025-03-01System Impact StudyBEPCCurrent status
GI-1404BillingsWind3832014-05-14In Progress (unknown study)WAPA/BEPC/HCPD Integrated SystemCurrent status
MPC04000OliverWind3002019-04-25IA ExecutedMinnkota Power CooperativeCurrent status
J3280DickeyWind3002024-04-17In Progress (unknown study)MONTANA-DAKOTA UTILITIES CO.Current status
GEN-2024-331DunnBattery3002025-03-01System Impact StudyBEPCCurrent status
MPC04500Grand ForksWind2582023-09-26Feasibility StudyMinnkota Power CooperativeCurrent status
GEN-2018-067WilliamsWind2552018-10-25IA ExecutedMWECCurrent status
GI-1503WilliamsWind2512015-03-23In Progress (unknown study)WAPA/BEPC/HCPD Integrated SystemCurrent status
MPC03800EddyWind2502019-02-21IA ExecutedMinnkota Power CooperativeCurrent status
J1040McintoshWind2502018-03-12ConstructionMONTANA-DAKOTA UTILITIES CO.Current status
GEN-2022-010WilliamsOther2502022-05-26Facility StudyBEPCCurrent status
GEN-2022-083WilliamsGas2502022-10-21Facility StudyBEPCCurrent status
GEN-2024-328SlopeBattery2502025-03-01System Impact StudyBEPCCurrent status
J3787StutsmanSolar2472024-04-16In Progress (unknown study)OTTER TAIL POWER COMPANYCurrent status
GEN-2024-326StarkBattery2252025-03-01System Impact StudyWAPACurrent status
MPC04600EddyBattery2092025-11-25In Progress (unknown study)Minnkota Power CooperativeCurrent status
MPC04400Grand ForksWind2062022-02-04System Impact StudyMinnkota Power CooperativeCurrent status
GEN-2016-004OliverWind2022016-03-10IA ExecutedBEPCCurrent status
J1588CassSolar2002024-04-30IA PendingNORTHERN STATES POWER COMPANYCurrent status
J2080OliverWind2002021-08-12Cluster StudyMINNESOTA POWER INC.Current status
J2250StutsmanWind2002021-11-01Cluster StudyMONTANA-DAKOTA UTILITIES CO.Current status
J3522CassSolar2002024-03-18In Progress (unknown study)ITC MIDWESTCurrent status
J3833CassWind2002024-10-01OTTER TAIL POWER COMPANYCurrent status
Surplus; J1588CassBattery2002025-03-25NORTHERN STATES POWER COMPANYCurrent status
GEN-2024-327WardBattery2002025-03-01System Impact StudyCPECCurrent status
GEN-2024-329WilliamsBattery2002025-03-01System Impact StudyMWECCurrent status
GEN-2024-284MercerSolar1992025-03-01System Impact StudyBEPCCurrent status
GI-1502StarkWind1822015-03-23In Progress (unknown study)WAPA/BEPC/HCPD Integrated SystemCurrent status
GEN-2024-034SargentBattery1752024-10-30System Impact StudyWAPACurrent status
J4170RichlandSolar+Battery1722025-10-07OTTER TAIL POWER COMPANYCurrent status
GI-1508MercerWind1722015-09-30In Progress (unknown study)WAPA/BEPC/HCPD Integrated SystemCurrent status
MPC03600RichlandSolar1702018-05-04IA ExecutedMinnkota Power CooperativeCurrent status
GEN-2023-SR4BurkeBattery1702022-12-15IA ExecutedBEPCCurrent status
MPC03900EddyWind1512019-04-16IA ExecutedMinnkota Power CooperativeCurrent status
J2502MortonWind1502022-09-13Cluster StudyMINNESOTA POWER INC.Current status
GEN-2019-037MercerSolar1502019-05-17IA ExecutedBEPCCurrent status
GEN-2020-091MckenzieSolar1502020-04-30IA ExecutedBEPCCurrent status
GI-1509StarkWind1502015-09-30In Progress (unknown study)WAPA/BEPC/HCPD Integrated SystemCurrent status
MPC03700RichlandSolar1302018-05-04IA ExecutedMinnkota Power CooperativeCurrent status
GEN-2022-009WilliamsOther1252022-05-26Facility StudyBEPCCurrent status
Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2MortonGas+Other1032019-06-24MONTANA-DAKOTA UTILITIES CO.Current status
J2097MortonWind1002021-08-25Cluster StudyMINNESOTA POWER INC.Current status
J2157MortonWind1002021-08-25Cluster StudyMINNESOTA POWER INC.Current status
J3070MortonWind1002022-09-15Cluster StudyMISOCurrent status
GEN-2017-214WardWind1002017-11-30IA ExecutedBEPCCurrent status
GEN-2017-215WardWind1002017-11-30IA ExecutedBEPCCurrent status
GEN-2024-359StarkBattery1002025-03-01System Impact StudyWAPACurrent status
J2913SargentBattery902022-09-15Cluster StudyOTTER TAIL POWER COMPANYCurrent status
J4077EmmonsSolar452025-10-06MONTANA-DAKOTA UTILITIES CO.Current status
J4070EmmonsSolar402025-10-07MONTANA-DAKOTA UTILITIES CO.Current status
GEN-2024-SR12LamoureBattery202024-05-21IA PendingWAPACurrent status
G150McintoshOther122001-11-13MISOCurrent status
GEN-2025-GR5WardWind82025-10-06In Progress (unknown study)WAPACurrent status
GI-1103BurkeGas12011-09-09IA ExecutedWAPA/BEPC/HCPD Integrated SystemCurrent status
GEN-2025-GR3McleanWind02025-10-06In Progress (unknown study)WAPACurrent status

Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0