Interconnection queue in Mississippi
Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.
This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.
LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.
Statewide
- Active capacity
- 16,124 MW
- Active requests
- 88
- Median years in queue (active)
- 3.3
- Withdrawn, of requests entered by 2020
- 75%
| Type | Active capacity (MW) | Projects |
|---|---|---|
| Solar | 7,510 | 50 |
| Wind | 947 | 5 |
| Storage | 1,920 | 12 |
| Gas | 3,344 | 6 |
| Hybrid | 2,404 | 15 |
By county
| County | Active capacity (MW) | Projects | Solar | Wind | Storage | Gas | Hybrid | Other | Median years in queue (active) | Withdrawn, of requests entered by 2020 |
|---|---|---|---|---|---|---|---|---|---|---|
| Desoto | 1,904 | 6 | 649 | 250 | 1,005 | 4.2 | ||||
| Sunflower | 1,669 | 11 | 849 | 570 | 250 | 3.3 | ||||
| Hinds | 1,366 | 3 | 150 | 820 | 396 | 4.4 | ||||
| Madison | 877 | 6 | 407 | 300 | 170 | 3.3 | ||||
| Clay | 850 | 5 | 400 | 450 | 5.7 | |||||
| Warren | 820 | 1 | 820 | 0.4 | ||||||
| Lowndes | 820 | 2 | 200 | 620 | 1.5 | 62% of 26 | ||||
| Jasper | 715 | 4 | 365 | 350 | 2.3 | |||||
| Tunica | 697 | 4 | 320 | 377 | 5.0 | |||||
| Washington | 670 | 3 | 500 | 170 | 0.3 | |||||
| Perry | 500 | 3 | 250 | 150 | 100 | 3.3 | ||||
| Quitman | 450 | 1 | 450 | 3.3 | ||||||
| Holmes | 425 | 2 | 225 | 200 | 3.3 | |||||
| Amite | 405 | 3 | 305 | 100 | 1.2 | |||||
| Bolivar | 360 | 3 | 260 | 100 | 3.3 | |||||
| Rankin | 340 | 2 | 140 | 200 | 0.7 | |||||
| Attala | 300 | 2 | 100 | 200 | 2.4 | |||||
| Chickasaw | 295 | 2 | 295 | 5.7 | ||||||
| Monroe | 235 | 3 | 160 | 75 | 8.6 | |||||
| Leflore | 200 | 1 | 200 | 3.3 | ||||||
| Coahoma | 200 | 1 | 200 | 0.3 | ||||||
| Tallahatchie | 200 | 2 | 100 | 100 | 4.4 | |||||
| Lee | 200 | 1 | 200 | 3.4 | ||||||
| Jefferson Davis | 173 | 1 | 173 | 4.4 | ||||||
| Simpson | 165 | 1 | 165 | 3.3 | ||||||
| Yazoo | 150 | 1 | 150 | 3.3 | ||||||
| Sharkey | 120 | 1 | 120 | 0.4 | ||||||
| Montgomery | 110 | 1 | 110 | 3.3 | ||||||
| Scott | 100 | 1 | 100 | 0.2 | ||||||
| Panola | 100 | 1 | 100 | 3.3 | ||||||
| Marion | 100 | 1 | 100 | 3.3 | ||||||
| Wayne | 100 | 1 | 100 | 0.7 | ||||||
| Covington | 96 | 1 | 96 | 7.8 | ||||||
| Pinola | 90 | 1 | 90 | 2.8 | ||||||
| Humphreys | 75 | 1 | 75 | 1.7 | ||||||
| Choctaw | 67 | 1 | 67 | 3.3 | ||||||
| Benton | 54 | 1 | 54 | 1.2 | ||||||
| Lamar | 52 | 1 | 52 | 8.7 | ||||||
| Marshall | 50 | 1 | 50 | 3.3 | ||||||
| Kemper | 25 | 1 | 25 | 0.7 | ||||||
| Forrest | 0 | 0 | ||||||||
| Pike | 0 | 0 | ||||||||
| George | 0 | 0 | ||||||||
| Wilkinson | 0 | 0 | ||||||||
| Carroll | 0 | 0 | ||||||||
| Jefferson | 0 | 0 | ||||||||
| Lincoln | 0 | 0 | ||||||||
| Walthall | 0 | 0 | ||||||||
| Franklin | 0 | 0 | ||||||||
| Copiah | 0 | 0 | ||||||||
| Yalobusha | 0 | 0 | ||||||||
| Greene | 0 | 0 | ||||||||
| Pearl River | 0 | 0 | ||||||||
| Clarke | 0 | 0 | ||||||||
| Jackson | 0 | 0 | ||||||||
| Hancock | 0 | 0 | ||||||||
| Stone | 0 | 0 | ||||||||
| Jones | 0 | 0 | ||||||||
| Lauderdale | 0 | 0 | ||||||||
| Newton | 0 | 0 | ||||||||
| Harrison | 0 | 0 | ||||||||
| Oktibbeha | 0 | 0 | ||||||||
| Union | 0 | 0 | ||||||||
| Itawamba | 0 | 0 | ||||||||
| Noxubee | 0 | 0 | ||||||||
| Pontotoc | 0 | 0 | ||||||||
| Winston | 0 | 0 | ||||||||
| Alcorn | 0 | 0 | ||||||||
| Calhoun | 0 | 0 | ||||||||
| Lafayette | 0 | 0 | ||||||||
| Leake | 0 | 0 |
Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.
Active requests
Status is as of Dec 31, 2025. Current status at Interconnection.fyi.
| Project | County | Type | MW | Entered the queue | Study phase | Utility or operator | Live status |
|---|---|---|---|---|---|---|---|
| J1813 | Desoto | Gas | 1,005 | 2022-07-07 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| Vicksburg CCCT | Warren | Gas | 820 | 2025-08-06 | In Progress (unknown study) | Entergy Mississippi, LLC | Current status |
| Lakeover CCCT | Hinds | Gas | 820 | 2025-08-06 | In Progress (unknown study) | Entergy Mississippi, LLC | Current status |
| 569 | Lowndes | Gas | 620 | 2023-06-20 | Facility Study | Tennessee Valley Authority | Current status |
| J2966 | Quitman | Solar | 450 | 2022-09-08 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2173 | Hinds | Solar+Battery | 396 | 2021-08-23 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J1946 | Jasper | Solar+Battery | 350 | 2021-08-19 | IA Pending | COOPERATIVE ENERGY | Current status |
| J3623 | Sunflower | Wind | 350 | 2024-04-17 | In Progress (unknown study) | ENTERGY MISSISSIPPI, LLC. | Current status |
| J4121 | Washington | Solar | 300 | 2025-09-19 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J2091 | Desoto | Battery | 250 | 2022-01-11 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2602 | Desoto | Solar | 250 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2999 | Perry | Solar | 250 | 2022-09-15 | Cluster Study | COOPERATIVE ENERGY | Current status |
| J3139 | Holmes | Solar | 225 | 2022-09-13 | Cluster Study | MISO | Current status |
| J1458 | Washington | Solar | 200 | 2019-04-29 | Construction | ENTERGY MISSISSIPPI | Current status |
| J1891 | Attala | Solar+Battery | 200 | 2021-08-19 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2289 | Sunflower | Solar | 200 | 2021-09-09 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2330 | Leflore | Solar | 200 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2893 | Holmes | Solar+Battery | 200 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J4073 | Coahoma | Solar | 200 | 2025-09-29 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J4119 | Rankin | Battery | 200 | 2025-09-23 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J4154 | Madison | Battery | 200 | 2025-10-07 | GridUnity | Current status | |
| J4189 | Sunflower | Solar | 200 | 2025-10-06 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J866 | Tunica | Wind | 200 | 2017-06-16 | Construction | Entergy | Current status |
| 25RSC-013 | Lowndes | Battery | 200 | 2025-08-01 | In Progress (unknown study) | Tennessee Valley Authority | Current status |
| 423 | Clay | Solar | 200 | 2020-04-21 | IA Executed | Tennessee Valley Authority | Current status |
| 429 | Clay | Battery | 200 | 2020-04-29 | IA Executed | Tennessee Valley Authority | Current status |
| 466 | Clay | Solar | 200 | 2021-02-08 | IA Executed | Tennessee Valley Authority | Current status |
| 512 | Lee | Solar | 200 | 2022-08-23 | Facility Study | Tennessee Valley Authority | Current status |
| 600 | Clay | Battery | 200 | 2023-12-10 | Facility Study | Tennessee Valley Authority | Current status |
| J2047 | Desoto | Solar | 199 | 2021-08-12 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J3049 | Madison | Solar | 188 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2571 | Tunica | Wind | 177 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2127 | Jefferson Davis | Solar+Battery | 173 | 2021-08-23 | IA Pending | COOPERATIVE ENERGY | Current status |
| J3764 | Madison | Solar+Battery | 170 | 2024-04-18 | In Progress (unknown study) | ENTERGY MISSISSIPPI, LLC. | Current status |
| S1127 | Washington | Battery | 170 | 2025-11-10 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J3053 | Madison | Solar | 169 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2873 | Simpson | Solar | 165 | 2022-09-13 | Cluster Study | COOPERATIVE ENERGY | Current status |
| J3987 | Amite | Solar | 165 | 2024-10-25 | MISO | Current status | |
| 25-IC-1355 | Jasper | Solar | 165 | 2025-04-16 | Cluster Study | Southern Company | Current status |
| J3900 | Sunflower | Wind | 163 | 2024-12-26 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J1440 | Tunica | Solar | 160 | 2019-04-29 | Construction | ENTERGY MISSISSIPPI | Current status |
| J3175 | Tunica | Solar | 160 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| IC-1145 | Jasper | Solar | 156 | 2023-06-09 | IA Executed | Southern Company | Current status |
| J1672 | Hinds | Solar | 150 | 2020-06-23 | IA Executed | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2720 | Yazoo | Solar | 150 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2740 | Sunflower | Solar | 150 | 2022-09-13 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2869 | Sunflower | Solar+Battery | 150 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J4083 | Perry | Battery | 150 | 2025-10-07 | COOPERATIVE ENERGY | Current status | |
| 425 | Chickasaw | Solar | 150 | 2020-04-23 | IA Executed | Tennessee Valley Authority | Current status |
| 422 | Chickasaw | Solar | 145 | 2020-04-02 | IA Executed | Tennessee Valley Authority | Current status |
| J3913 | Amite | Solar | 140 | 2024-10-25 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| 672 | Rankin | Solar | 140 | 2024-10-30 | Cluster Study | Tennessee Valley Authority | Current status |
| J2287 | Bolivar | Solar | 135 | 2021-09-07 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2751 | Bolivar | Solar | 125 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2685 | Sharkey | Solar | 120 | 2025-08-21 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2752 | Montgomery | Solar | 110 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J1748 | Desoto | Solar | 100 | 2020-07-17 | IA Executed | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2297 | Sunflower | Solar | 100 | 2021-09-09 | IA Pending | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2761 | Marion | Solar | 100 | 2022-09-15 | Cluster Study | COOPERATIVE ENERGY | Current status |
| J2763 | Sunflower | Solar+Battery | 100 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J2957 | Panola | Solar+Battery | 100 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J3028 | Perry | Solar+Battery | 100 | 2022-09-14 | Cluster Study | COOPERATIVE ENERGY | Current status |
| J3093 | Madison | Battery | 100 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J3186 | Bolivar | Solar+Battery | 100 | 2022-09-15 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J3231 | Amite | Solar+Battery | 100 | 2022-09-14 | Cluster Study | ENTERGY MISSISSIPPI, LLC. | Current status |
| J4046 | Attala | Solar | 100 | 2025-07-17 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J4131 | Scott | Battery | 100 | 2025-10-01 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| J908 | Tallahatchie | Solar | 100 | 2017-06-16 | Construction | Entergy | Current status |
| J962 | Desoto | Solar | 100 | 2018-03-12 | Construction | ENTERGY MISSISSIPPI | Current status |
| Surplus; J908 | Tallahatchie | Battery | 100 | 2025-08-31 | ENTERGY MISSISSIPPI, LLC. | Current status | |
| 25-IC-1337 | Wayne | Solar+Battery | 100 | 2025-04-14 | Cluster Study | Southern Company | Current status |
| 313 | Monroe | Solar | 100 | 2017-05-23 | IA Executed | Tennessee Valley Authority | Current status |
| J604 | Sunflower | Solar | 100 | 2016-05-09 | IA Executed | MISO | Current status |
| J1294 | Sunflower | Solar | 99 | 2019-04-29 | Construction | ENTERGY MISSISSIPPI | Current status |
| J1144 | Covington | Solar | 96 | 2018-03-12 | Construction | COOPERATIVE ENERGY | Current status |
| 530 | Pinola | Solar+Battery | 90 | 2023-03-07 | IA Executed | Tennessee Valley Authority | Current status |
| J3590 | Humphreys | Solar | 75 | 2024-04-17 | In Progress (unknown study) | ENTERGY MISSISSIPPI, LLC. | Current status |
| 671 | Monroe | Solar+Battery | 75 | 2024-10-30 | Cluster Study | Tennessee Valley Authority | Current status |
| 522 | Choctaw | Solar | 67 | 2022-09-23 | Facility Study | Tennessee Valley Authority | Current status |
| 314 | Monroe | Solar | 60 | 2017-05-23 | IA Executed | Tennessee Valley Authority | Current status |
| J3592 | Sunflower | Wind | 57 | 2024-04-18 | In Progress (unknown study) | ENTERGY MISSISSIPPI, LLC. | Current status |
| 656 | Benton | Gas | 54 | 2024-10-01 | Cluster Study | Tennessee Valley Authority | Current status |
| J791 | Lamar | Solar | 52 | 2017-04-24 | IA Executed | MISO | Current status |
| J1747 | Madison | Solar | 50 | 2020-06-23 | Construction | ENTERGY MISSISSIPPI, LLC. | Current status |
| 424 | Clay | Battery | 50 | 2020-04-21 | IA Executed | Tennessee Valley Authority | Current status |
| 519 | Marshall | Solar | 50 | 2022-09-02 | IA Executed | Tennessee Valley Authority | Current status |
| IC-1203 | Jasper | Solar | 44 | 2023-11-20 | IA Executed | Southern Company | Current status |
| 25-IC-1316 | Kemper | Gas | 25 | 2025-04-11 | Cluster Study | Southern Company | Current status |
Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by May 7, 2027. Last checked for an update: Oct 31, 2026.