Interconnection queue in Missouri
Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.
This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.
LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.
Statewide
- Active capacity
- 29,653 MW
- Active requests
- 124
- Median years in queue (active)
- 2.7
- Withdrawn, of requests entered by 2020
- 70%
| Type | Active capacity (MW) | Projects |
|---|---|---|
| Solar | 7,911 | 40 |
| Wind | 3,447 | 10 |
| Storage | 5,802 | 31 |
| Gas | 7,521 | 18 |
| Hybrid | 3,243 | 15 |
| Other | 1,730 | 10 |
By county
| County | Active capacity (MW) | Projects | Solar | Wind | Storage | Gas | Hybrid | Other | Median years in queue (active) | Withdrawn, of requests entered by 2020 |
|---|---|---|---|---|---|---|---|---|---|---|
| Randolph | 5,038 | 15 | 445 | 1,518 | 1,380 | 115 | 1,580 | 6.2 | ||
| St. Charles | 2,220 | 1 | 2,220 | 0.7 | ||||||
| Jackson | 2,154 | 10 | 1,099 | 1,005 | 50 | 1.0 | ||||
| Nodaway | 1,369 | 4 | 468 | 901 | 4.5 | |||||
| Henry | 1,300 | 4 | 750 | 400 | 150 | 3.3 | ||||
| Clay | 1,150 | 6 | 1,150 | 2.6 | ||||||
| Clinton | 995 | 3 | 995 | 3.4 | ||||||
| St. Louis | 923 | 2 | 923 | 1.3 | ||||||
| Callaway | 850 | 3 | 550 | 300 | 5.5 | |||||
| Bollinger | 800 | 4 | 200 | 150 | 450 | 2.5 | ||||
| Jasper | 664 | 5 | 150 | 200 | 314 | 2.2 | ||||
| Audrain | 650 | 2 | 650 | 4.4 | ||||||
| Sullivan | 610 | 2 | 610 | 0.6 | ||||||
| Macon | 608 | 3 | 608 | 3.8 | ||||||
| Lincoln | 608 | 3 | 350 | 258 | 0.8 | |||||
| Scott | 556 | 3 | 556 | 6.7 | ||||||
| Greene | 544 | 3 | 399 | 145 | 0.8 | |||||
| Warren | 500 | 2 | 500 | 5.6 | ||||||
| New Madrid | 462 | 6 | 150 | 200 | 72 | 40 | 3.2 | |||
| Butler | 460 | 1 | 460 | 0.4 | ||||||
| Ralls | 455 | 3 | 455 | 0.9 | ||||||
| Adair | 450 | 2 | 450 | 3.7 | ||||||
| Cape Girardeau | 450 | 2 | 200 | 250 | 4.8 | |||||
| Marion | 440 | 2 | 440 | 2.2 | ||||||
| Gasconade | 440 | 2 | 300 | 140 | 2.5 | |||||
| Stoddard | 425 | 2 | 425 | 5.5 | ||||||
| Daviess | 400 | 2 | 200 | 200 | 1.7 | |||||
| Maries | 340 | 2 | 340 | 1.9 | ||||||
| Cass | 309 | 2 | 280 | 29 | 3.3 | |||||
| Knox | 300 | 1 | 300 | 7.8 | ||||||
| Dade | 247 | 1 | 247 | 5.1 | ||||||
| Atchison | 246 | 1 | 246 | 10.3 | ||||||
| Polk | 200 | 1 | 200 | 6.7 | ||||||
| Schuyler | 200 | 1 | 200 | 0.2 | ||||||
| Grundy | 200 | 1 | 200 | 0.7 | ||||||
| Montgomery | 200 | 2 | 200 | 5.5 | ||||||
| Cooper | 200 | 2 | 120 | 80 | 2.0 | |||||
| Buchanan | 200 | 1 | 200 | 0.8 | ||||||
| Barton | 200 | 1 | 200 | 0.8 | ||||||
| Ray | 199 | 1 | 199 | 0.8 | ||||||
| Vernon | 175 | 1 | 175 | 1.2 | ||||||
| Lawrence | 167 | 1 | 167 | 1.2 | ||||||
| Chariton | 150 | 1 | 150 | 2.2 | ||||||
| Barry | 130 | 1 | 130 | 8.1 | ||||||
| Osage | 100 | 1 | 100 | 1.7 | ||||||
| Saline | 100 | 1 | 100 | 0.8 | ||||||
| Carroll | 96 | 1 | 96 | 5.4 | ||||||
| Pettis | 95 | 1 | 95 | 4.7 | ||||||
| Iron | 60 | 1 | 60 | 6.7 | ||||||
| Gentry | 18 | 1 | 18 | 8.7 | ||||||
| Douglas | 0 | 0 | ||||||||
| Caldwell | 0 | 0 | ||||||||
| Mississippi | 0 | 0 | ||||||||
| St Clair | 0 | 0 | ||||||||
| Dekalb | 0 | 0 | ||||||||
| Pemiscot | 0 | 0 | ||||||||
| Dunklin | 0 | 0 | ||||||||
| Howard | 0 | 0 | ||||||||
| Miller | 0 | 0 | ||||||||
| Putnam | 0 | 0 | ||||||||
| Franklin | 0 | 0 | ||||||||
| Monroe | 0 | 0 | ||||||||
| Perry | 0 | 0 | ||||||||
| Boone | 0 | 0 | ||||||||
| St. Francois | 0 | 0 | ||||||||
| Moniteau | 0 | 0 | ||||||||
| Pike | 0 | 0 | ||||||||
| Jefferson | 0 | 0 | ||||||||
| Washington | 0 | 0 | ||||||||
| Clark | 0 | 0 | ||||||||
| Madison | 0 | 0 | ||||||||
| Mercer | 0 | 0 | ||||||||
| Platte | 0 | 0 | ||||||||
| Holt | 0 | 0 | ||||||||
| Lafayette | 0 | 0 | ||||||||
| Bates | 0 | 0 | ||||||||
| Newton | 0 | 0 | ||||||||
| Johnson | 0 | 0 | ||||||||
| Linn | 0 | 0 | ||||||||
| Cedar | 0 | 0 | ||||||||
| Andrew | 0 | 0 | ||||||||
| Christian | 0 | 0 | ||||||||
| Mcdonald | 0 | 0 |
Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.
Active requests
Status is as of Dec 31, 2025. Current status at Interconnection.fyi.
| Project | County | Type | MW | Entered the queue | Study phase | Utility or operator | Live status |
|---|---|---|---|---|---|---|---|
| J3996 | St. Charles | Gas | 2,220 | 2025-04-29 | AMEREN MISSOURI | Current status | |
| GI-83 | Randolph | Wind | 1,018 | 2019-06-19 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| J1490 | Randolph | Other | 1,000 | 2019-04-29 | IA Executed | Ameren Missouri | Current status |
| Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff | St. Louis | Gas+Other | 824 | 2024-05-28 | AMEREN MISSOURI | Current status | |
| GEN-2024-207 | Jackson | Gas | 779 | 2025-03-01 | System Impact Study | City of Independence MO | Current status |
| GI-122 | Randolph | Wind | 500 | 2024-05-20 | Facility Study | Associated Electric Cooperative, Incorporated | Current status |
| J1488 | Randolph | Other | 500 | 2019-04-29 | IA Executed | Ameren Missouri | Current status |
| GI-101 | Clinton | Gas | 460 | 2022-07-21 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-121 | Randolph | Gas | 460 | 2024-05-01 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-126 | Randolph | Gas | 460 | 2025-01-06 | System Impact Study | Associated Electric Cooperative, Incorporated | Current status |
| GI-128 | Clinton | Gas | 460 | 2025-07-25 | System Impact Study | Associated Electric Cooperative, Incorporated | Current status |
| GI-131 | Randolph | Gas | 460 | 2025-07-25 | System Impact Study | Associated Electric Cooperative, Incorporated | Current status |
| GI-132 | Butler | Gas | 460 | 2025-07-25 | System Impact Study | Associated Electric Cooperative, Incorporated | Current status |
| ERAS-2025-007 | Nodaway | Gas | 451 | 2025-10-02 | In Progress (unknown study) | WERE | Current status |
| ERAS-2025-013 | Nodaway | Gas | 451 | 2025-09-30 | In Progress (unknown study) | WERE | Current status |
| J1026 | Audrain | Wind | 400 | 2018-03-12 | IA Executed | Ameren Missouri | Current status |
| GEN-2017-108 | Henry | Solar | 400 | 2017-08-26 | IA Executed | KCPL | Current status |
| GEN-2025-SR1 | Henry | Battery | 400 | 2025-04-04 | Facility Study | KCPL | Current status |
| GEN-2024-289 | Henry | Solar | 350 | 2025-03-01 | System Impact Study | WERE | Current status |
| E0013 | Sullivan | Solar | 310 | 2025-08-06 | In Progress (unknown study) | Ameren Missouri | Current status |
| J1025 | Knox | Wind | 300 | 2018-03-12 | IA Executed | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J1836 | Callaway | Solar | 300 | 2020-06-23 | IA Pending | AMEREN MISSOURI | Current status |
| J2205 | Callaway | Solar+Battery | 300 | 2021-08-12 | Cluster Study | AMEREN MISSOURI | Current status |
| J3199 | Adair | Solar+Battery | 300 | 2022-09-15 | Cluster Study | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J3518 | Gasconade | Battery | 300 | 2024-04-19 | AMEREN MISSOURI | Current status | |
| J3758 | Macon | Solar | 300 | 2024-04-18 | In Progress (unknown study) | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J3957 | Sullivan | Solar | 300 | 2025-04-17 | AMEREN MISSOURI | Current status | |
| J976 | Warren | Solar | 300 | 2018-03-12 | Construction | Ameren Missouri | Current status |
| GEN-2022-073 | Clay | Battery | 300 | 2022-09-02 | Facility Study | KCPL | Current status |
| GEN-2024-170 | Cass | Battery | 280 | 2025-03-01 | System Impact Study | WERE | Current status |
| E0017 | Lincoln | Battery | 258 | 2025-08-06 | In Progress (unknown study) | Ameren Missouri | Current status |
| J1145 | Callaway | Solar | 250 | 2018-03-12 | IA Executed | Ameren Missouri | Current status |
| J2691 | Bollinger | Solar+Wind+Battery | 250 | 2022-09-15 | Cluster Study | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J3352 | Cape Girardeau | Battery | 250 | 2024-04-16 | In Progress (unknown study) | AMEREN MISSOURI | Current status |
| J3929 | Audrain | Wind | 250 | 2025-01-31 | AMEREN MISSOURI | Current status | |
| ERAS-2025-034 | Jasper | Gas | 250 | 2025-09-29 | In Progress (unknown study) | EMDE | Current status |
| GEN-2024-217 | Jackson | Battery | 250 | 2025-03-01 | System Impact Study | WERE | Current status |
| GEN-2024-370 | Clay | Battery | 250 | 2025-03-01 | System Impact Study | WERE | Current status |
| GI-95 | Dade | Wind | 247 | 2020-12-04 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| J476 | Atchison | Wind | 246 | 2015-09-14 | IA Executed | MISO | Current status |
| GI-120 | Randolph | Solar | 245 | 2024-04-29 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| J4001 | Marion | Solar | 245 | 2025-04-29 | MISO | Current status | |
| GI-53 | Nodaway | Wind | 238 | 2016-05-02 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-61 | Nodaway | Wind | 230 | 2017-05-03 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GEN-2024-206 | Jackson | Gas | 226 | 2025-03-01 | System Impact Study | City of Independence MO | Current status |
| J1034 | Stoddard | Solar | 225 | 2018-03-12 | Construction | Ameren Missouri | Current status |
| J2050 | Macon | Solar | 208 | 2022-03-28 | Cluster Study | AMEREN MISSOURI | Current status |
| J1087 | Scott | Solar | 200 | 2018-03-12 | Construction | Ameren Missouri | Current status |
| J1107 | Cape Girardeau | Solar | 200 | 2018-03-12 | Construction | Ameren Missouri | Current status |
| J1299 | Scott | Solar | 200 | 2019-04-29 | Construction | Ameren Missouri | Current status |
| J1519 | Bollinger | Solar | 200 | 2020-06-18 | IA Pending | AMEREN MISSOURI | Current status |
| J2238 | Maries | Solar+Battery | 200 | 2025-07-16 | Cluster Study | AMEREN MISSOURI | Current status |
| J2265 | Bollinger | Solar+Battery | 200 | 2025-07-16 | Cluster Study | AMEREN MISSOURI | Current status |
| J2524 | Stoddard | Solar | 200 | 2022-09-15 | Cluster Study | AMEREN MISSOURI | Current status |
| J2806 | Warren | Solar | 200 | 2022-09-13 | Cluster Study | AMEREN MISSOURI | Current status |
| J3436 | Daviess | Solar | 200 | 2024-04-17 | In Progress (unknown study) | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J3440 | Daviess | Battery | 200 | 2024-04-17 | In Progress (unknown study) | AMEREN TRANSMISSION COMPANY OF ILLINOIS | Current status |
| J3919 | Lincoln | Solar | 200 | 2025-03-07 | AMEREN MISSOURI | Current status | |
| J3959 | Grundy | Solar | 200 | 2025-04-17 | AMEREN MISSOURI | Current status | |
| J4090 | Schuyler | Solar | 200 | 2025-10-07 | GridUnity | Current status | |
| J956 | Ralls | Solar | 200 | 2018-03-09 | IA Executed | Ameren Missouri | Current status |
| Surplus; J944 | New Madrid | Battery | 200 | 2025-08-31 | ENTERGY ARKANSAS | Current status | |
| GEN-2019-016 | Polk | Solar | 200 | 2019-04-30 | IA Executed | EDE | Current status |
| GEN-2022-142 | Clay | Battery | 200 | 2023-02-21 | Facility Study | KCPL | Current status |
| GEN-2022-144 | Jackson | Battery | 200 | 2023-02-21 | Facility Study | KCPL | Current status |
| GEN-2023-033 | Clay | Battery | 200 | 2023-10-02 | Facility Study | WERE | Current status |
| GEN-2024-074 | Jackson | Battery | 200 | 2024-10-30 | System Impact Study | WERE | Current status |
| GEN-2024-175 | Greene | Battery | 200 | 2025-03-01 | System Impact Study | SPRM | Current status |
| GEN-2024-259 | Barton | Solar+Battery | 200 | 2025-03-01 | System Impact Study | EMDE | Current status |
| GEN-2024-260 | Buchanan | Battery | 200 | 2025-03-01 | System Impact Study | WERE | Current status |
| GEN-2024-167 | Ray | Battery | 199 | 2025-03-01 | System Impact Study | WERE | Current status |
| GEN-2024-181 | Greene | Battery | 199 | 2025-03-01 | System Impact Study | SPRM | Current status |
| GEN-2024-352 | Jackson | Battery | 199 | 2025-03-01 | System Impact Study | WERE | Current status |
| J1948 | Marion | Solar | 195 | 2022-03-23 | Cluster Study | MISO | Current status |
| J2288 | Ralls | Solar | 175 | 2025-01-27 | Cluster Study | AMEREN MISSOURI | Current status |
| GEN-2024-055 | Vernon | Solar | 175 | 2024-10-30 | System Impact Study | WERE | Current status |
| GEN-2024-084 | Lawrence | Battery | 167 | 2024-10-30 | System Impact Study | EMDE | Current status |
| J3442 | Scott | Solar | 156 | 2024-04-16 | In Progress (unknown study) | MISO | Current status |
| J1268 | Lincoln | Solar | 150 | 2019-04-29 | IA Executed | Ameren Missouri | Current status |
| J2142 | Adair | Solar+Battery | 150 | 2021-11-03 | Cluster Study | AMEREN MISSOURI | Current status |
| J2155 | New Madrid | Solar | 150 | 2022-03-28 | Cluster Study | AMEREN MISSOURI | Current status |
| J3505 | Bollinger | Battery | 150 | 2024-04-16 | In Progress (unknown study) | MISO | Current status |
| GEN-2020-072 | Henry | Solar+Battery | 150 | 2020-04-30 | IA Executed | GMO | Current status |
| GEN-2020-088 | Jasper | Solar | 150 | 2020-04-30 | IA Executed | EDE | Current status |
| GEN-2023-170 | Chariton | Battery | 150 | 2023-10-02 | Facility Study | WERE | Current status |
| GEN-2023-171 | Jackson | Battery | 150 | 2023-10-02 | Facility Study | INDN | Current status |
| GEN-2024-088 | Greene | Gas | 145 | 2024-10-30 | System Impact Study | SPRM | Current status |
| J2593 | Gasconade | Solar+Battery | 140 | 2022-09-14 | Cluster Study | AMEREN MISSOURI | Current status |
| J3229 | Maries | Solar+Battery | 140 | 2022-09-14 | Cluster Study | AMEREN MISSOURI | Current status |
| GEN-2017-188 | Barry | Solar | 130 | 2017-11-30 | IA Executed | EDE | Current status |
| GEN-2024-054 | Cooper | Solar | 120 | 2024-10-30 | System Impact Study | WERE | Current status |
| J2382 | Randolph | Solar+Battery | 115 | 2022-09-14 | Cluster Study | AMEREN MISSOURI | Current status |
| GI-86 | Randolph | Solar | 100 | 2019-10-25 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-90 | Randolph | Solar | 100 | 2020-07-24 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-93 | Macon | Solar | 100 | 2020-11-10 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| J1352 | Montgomery | Solar | 100 | 2019-04-29 | IA Executed | Ameren Missouri | Current status |
| J2179 | Montgomery | Solar | 100 | 2021-08-06 | Cluster Study | AMEREN MISSOURI | Current status |
| J3736 | Osage | Battery | 100 | 2024-04-17 | In Progress (unknown study) | MISO | Current status |
| GEN-2022-102 | Clay | Battery | 100 | 2023-01-06 | Facility Study | KCPL | Current status |
| GEN-2023-061 | Jasper | Battery | 100 | 2023-10-02 | Facility Study | SWPA | Current status |
| GEN-2024-090 | Clay | Battery | 100 | 2024-10-30 | System Impact Study | WERE | Current status |
| GEN-2024-091 | Jasper | Battery | 100 | 2024-10-30 | System Impact Study | EDE | Current status |
| GEN-2024-375 | Saline | Battery | 100 | 2025-03-01 | System Impact Study | WERE | Current status |
| Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4 | St. Louis | Other+Battery | 99 | 2024-12-16 | AMEREN MISSOURI | Current status | |
| GI-91 | Carroll | Solar | 96 | 2020-07-24 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GEN-2021-077 | Pettis | Solar+Battery | 95 | 2021-04-30 | Facility Study | GMO | Current status |
| GI-127 | Ralls | Solar | 80 | 2025-05-22 | Facility Study | Associated Electric Cooperative, Incorporated | Current status |
| GEN-2022-100 | Cooper | Solar+Battery | 80 | 2023-03-24 | Facility Study | KCPL | Current status |
| GI-102 | Clinton | Gas | 75 | 2022-07-21 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GEN-2020-064 | Jasper | Gas | 64 | 2020-04-22 | IA Executed | EDE | Current status |
| J1213 | Iron | Hydro | 60 | 2019-04-27 | IA Executed | Ameren Missouri | Current status |
| GEN-2018-031 | Jackson | Battery | 50 | 2018-05-29 | IA Executed | INDN | Current status |
| GEN-2021-042 | Jackson | Battery | 50 | 2021-04-30 | IA Executed | INDN | Current status |
| GEN-2025-SR18 | Jackson | Other | 50 | 2025-06-12 | In Progress (unknown study) | INDN | Current status |
| GI-117 | New Madrid | Gas | 46 | 2023-05-03 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-48 | Randolph | Coal | 33 | 2012-10-08 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
| GEN-2020-061 | Cass | Gas | 29 | 2020-04-28 | IA Executed | GMO | Current status |
| GI-43 | Randolph | Coal | 28 | 2009-11-04 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
| GI-116 | New Madrid | Gas | 26 | 2023-05-03 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-39 | New Madrid | Coal | 20 | 2009-10-24 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
| GI-40 | New Madrid | Coal | 20 | 2009-10-24 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
| GI-60 | Gentry | Wind | 18 | 2017-04-04 | IA Executed | Associated Electric Cooperative, Incorporated | Current status |
| GI-41 | Randolph | Coal | 17 | 2009-10-24 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
| GI-42 | Randolph | Coal | 2 | 2009-11-04 | In Progress (unknown study) | Associated Electric Cooperative, Incorporated | Current status |
Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by May 7, 2027. Last checked for an update: Oct 31, 2026.