gridprims

as of Oct 27, 2026

Interconnection queue

Interconnection queue in Florida

Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.

This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.

LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.

Statewide

Active capacity
23,030 MW
Active requests
232
Median years in queue (active)
3.0
Withdrawn, of requests entered by 2020
59%
Active capacity by type
TypeActive capacity (MW)Projects
Solar14,550198
Storage1,76810
Gas3,46913
Hybrid5827
Other2,6614

By county

Queue requests by county in Florida, as of Dec 31, 2025
CountyActive capacity (MW)ProjectsSolarWindStorageGasHybridOtherMedian years in queue (active)Withdrawn, of requests entered by 2020
Hendry2,980402,9803.0
Miami-Dade2,6753752,60018.3
Osceola1,99593731,6222.774% of 23
St. Lucie1,714231,7143.7
Desoto1,193161,1933.4
Collier1,118151,1182.4
Charlotte1,045141,0453.0
Martin1,02914969603.0
Duval9956506453003.1
Pasco862475199575134.3
Manatee6839596873.8
Indian River59685963.4
Polk48582012084132482.167% of 63
Brevard44942242257.4
Bay40014002.0
Pinellas39722251723.7
Highlands32442241005.0
Suwannee30043002.581% of 26
Madison29942991.5
Citrus29922991.465% of 20
Hillsborough29842981.260% of 30
Orange2975285122.0
Putnam2752752003.7
Leon24931491004.4
Jackson150275753.4
Sumter15021502.1
Liberty15021500.6
Gilchrist14921497.3
Gadsden14921495.7
Baker14921496.9
Levy14521458.381% of 21
County not given138221368.978% of 23
Volusia761765.3
Marion751756.3
Hamilton751751.1
Bradford751754.4
Alachua751755.785% of 20
Columbia751759.4
Nassau751757.9
Union751758.5
Okeechobee751755.4
St Lucie751757.6
Calhoun751753.4
Walton751755.9
Gulf00
Quincy00
Hernando00
Lake00
Taylor00
Hardee00
Gilcrhist00
Jefferson00
Dixie00
Wakulla00
Highland00
Perry00
Broward00
Escambia00
Palm Beach00
St. Johns00
Clay00
Okaloosa00
St Johns00
Flagler00
Santa Rosa00
Washington00
Lee00
Holmes00

Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.

Active requests

Status is as of Dec 31, 2025. Current status at Interconnection.fyi.

Active interconnection requests in Florida
ProjectCountyTypeMWEntered the queueStudy phaseUtility or operatorLive status
107Miami-DadeNuclear1,3002007-08-30Facility StudyFlorida Power & LightCurrent status
108Miami-DadeNuclear1,3002007-08-30Facility StudyFlorida Power & LightCurrent status
JEA-Q008DuvalGas6452018-02-22Feasibility StudyJacksonville Electric AuthorityCurrent status
137PascoGas5752015-11-10ConstructionDuke Energy FloridaCurrent status
Bull Creek (Osceola Generating Station)OsceolaGas5552021-09-28IA ExecutedOrlando Utilities CommissionCurrent status
4OsceolaGas5371999-04-22In Progress (unknown study)Duke Energy FloridaCurrent status
620BayBattery4002024-01-08System Impact StudyFlorida Power & LightCurrent status
FC100382OsceolaGas2652025-12-12In Progress (unknown study)Duke Energy FloridaCurrent status
FC100386OsceolaGas2652025-12-15In Progress (unknown study)Duke Energy FloridaCurrent status
292PinellasBattery2252021-04-07ConstructionDuke Energy FloridaCurrent status
Malta ProjectBrevardBattery2252023-03-06Facility StudyOrlando Utilities CommissionCurrent status
615PutnamBattery2002024-01-08System Impact StudyFlorida Power & LightCurrent status
FC100009PascoBattery1992024-12-05IA PendingDuke Energy FloridaCurrent status
FC100380CitrusBattery1992025-12-08In Progress (unknown study)Duke Energy FloridaCurrent status
328PinellasGas1722023-06-07ConstructionDuke Energy FloridaCurrent status
22Gas1362018-08-30System Impact StudySeminole Electric CooperativeCurrent status
118PolkGas+Coal1322025-04-10Cluster StudyTampa Electric CompanyCurrent status
327CitrusBattery1002023-05-05ConstructionDuke Energy FloridaCurrent status
FC100008HighlandsBattery1002024-12-05IA PendingDuke Energy FloridaCurrent status
FC100381LeonBattery1002025-12-08In Progress (unknown study)Duke Energy FloridaCurrent status
415ManateeGas872020-09-14Facility StudyFlorida Power & LightCurrent status
333PolkGas842023-07-21ConstructionDuke Energy FloridaCurrent status
417VolusiaGas762020-09-18Facility StudyFlorida Power & LightCurrent status
425AJacksonSolar+Battery752022-02-07IA ExecutedFlorida Power & LightCurrent status
202.1LevySolar752017-10-16ConstructionDuke Energy FloridaCurrent status
218SuwanneeSolar752018-02-20Facility StudyDuke Energy FloridaCurrent status
258HighlandsSolar752019-05-31ConstructionDuke Energy FloridaCurrent status
259HighlandsSolar752019-05-31ConstructionDuke Energy FloridaCurrent status
269MarionSolar752019-09-30Facility StudyDuke Energy FloridaCurrent status
273PolkSolar752019-12-17ConstructionDuke Energy FloridaCurrent status
290SuwanneeSolar752020-12-30System Impact StudyDuke Energy FloridaCurrent status
322SumterSolar752022-12-16ConstructionDuke Energy FloridaCurrent status
323JacksonSolar752023-02-13ConstructionDuke Energy FloridaCurrent status
325OsceolaSolar752023-05-03ConstructionDuke Energy FloridaCurrent status
326OsceolaSolar752023-05-03ConstructionDuke Energy FloridaCurrent status
341OrangeSolar752024-01-13ConstructionDuke Energy FloridaCurrent status
342OrangeSolar752024-01-13ConstructionDuke Energy FloridaCurrent status
343OrangeSolar752024-01-13ConstructionDuke Energy FloridaCurrent status
344MadisonSolar752024-01-12ConstructionDuke Energy FloridaCurrent status
FC100004SumterSolar752024-11-27IA PendingDuke Energy FloridaCurrent status
FC100006MadisonSolar752024-11-27Facility StudyDuke Energy FloridaCurrent status
FC100007MadisonSolar752024-11-27Facility StudyDuke Energy FloridaCurrent status
FC100012HamiltonSolar752024-11-27Facility StudyDuke Energy FloridaCurrent status
FC100018LibertySolar752024-12-13Facility StudyDuke Energy FloridaCurrent status
FC100383LibertySolar752025-12-12In Progress (unknown study)Duke Energy FloridaCurrent status
FC100384SuwanneeSolar752025-12-12In Progress (unknown study)Duke Energy FloridaCurrent status
FC100385SuwanneeSolar752025-12-12In Progress (unknown study)Duke Energy FloridaCurrent status
425BradfordSolar+Battery752021-08-20IA ExecutedFlorida Power & LightCurrent status
604DesotoSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
605DesotoSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
607CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
608CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
609CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
610CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
611CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
612CharlotteSolar752023-12-15System Impact StudyFlorida Power & LightCurrent status
JEA-Q009DuvalSolar+Battery752021-07-07In Progress (unknown study)Jacksonville Electric AuthorityCurrent status
JEA-Q010DuvalSolar+Battery752024-05-09Feasibility StudyJacksonville Electric AuthorityCurrent status
JEA-Q011DuvalSolar+Battery752024-05-09Feasibility StudyJacksonville Electric AuthorityCurrent status
JEA-Q012DuvalSolar+Battery752024-05-09Feasibility StudyJacksonville Electric AuthorityCurrent status
151ColumbiaSolar752016-07-27Facility StudyDuke Energy FloridaCurrent status
171GilchristSolar752016-12-21Facility StudyDuke Energy FloridaCurrent status
236GadsdenSolar752018-07-17System Impact StudyDuke Energy FloridaCurrent status
237PascoSolar752018-07-17System Impact StudyDuke Energy FloridaCurrent status
284AlachuaSolar752020-04-21System Impact StudyDuke Energy FloridaCurrent status
286GilchristSolar752020-06-02Facility StudyDuke Energy FloridaCurrent status
191ManateeSolar752016-05-09Facility StudyFlorida Power & LightCurrent status
276UnionSolar752017-06-27Facility StudyFlorida Power & LightCurrent status
280HendrySolar752017-06-27Facility StudyFlorida Power & LightCurrent status
289Miami-DadeSolar752017-06-27Facility StudyFlorida Power & LightCurrent status
306BrevardSolar752017-06-27Facility StudyFlorida Power & LightCurrent status
333NassauSolar752018-02-13Facility StudyFlorida Power & LightCurrent status
339HendrySolar752018-03-21Facility StudyFlorida Power & LightCurrent status
344BakerSolar752018-05-04Facility StudyFlorida Power & LightCurrent status
347St LucieSolar752018-05-23Facility StudyFlorida Power & LightCurrent status
357BrevardSolar752018-07-30Facility StudyFlorida Power & LightCurrent status
358BrevardSolar752018-07-30Facility StudyFlorida Power & LightCurrent status
376BakerSolar752019-11-22Facility StudyFlorida Power & LightCurrent status
378HWaltonSolar752020-02-05Facility StudyFlorida Power & LightCurrent status
398PutnamSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
404St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
405OkeechobeeSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
406St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
407St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
408St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
410St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
411St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
412St. LucieSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
413DesotoSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
414DesotoSolar752020-07-21Facility StudyFlorida Power & LightCurrent status
424ManateeSolar752021-05-11Facility StudyFlorida Power & LightCurrent status
424ALeonSolar752021-08-05Facility StudyFlorida Power & LightCurrent status
424BLeonSolar752021-08-05Facility StudyFlorida Power & LightCurrent status
424DMadisonSolar752021-08-05Facility StudyFlorida Power & LightCurrent status
425BGadsdenSolar752022-02-15Facility StudyFlorida Power & LightCurrent status
427Indian RiverSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
428ManateeSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
429DesotoSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
430DesotoSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
431HendrySolar752022-03-02Facility StudyFlorida Power & LightCurrent status
432Indian RiverSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
433ManateeSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
434DesotoSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
437ManateeSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
438HendrySolar752022-03-02Facility StudyFlorida Power & LightCurrent status
439DesotoSolar752022-03-02Facility StudyFlorida Power & LightCurrent status
444St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
445St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
446St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
447St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
448St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
449St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
450St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
451St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
452Indian RiverSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
453St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
454St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
455St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
456Indian RiverSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
457St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
458St. LucieSolar752022-04-06Facility StudyFlorida Power & LightCurrent status
459CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
460CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
461CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
462CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
463CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
464CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
465CollierSolar752022-04-21Facility StudyFlorida Power & LightCurrent status
471DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
472DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
473DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
474DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
475DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
476DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
477DesotoSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
478HighlandsSolar752022-07-20Facility StudyFlorida Power & LightCurrent status
489CalhounSolar752022-08-09Facility StudyFlorida Power & LightCurrent status
490St. LucieSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
491Indian RiverSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
492Indian RiverSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
493Indian RiverSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
496MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
497MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
498MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
499MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
500MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
501MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
502MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
503MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
504MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
505MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
506MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
507MartinSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
509ManateeSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
510ManateeSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
511ManateeSolar752023-01-06Facility StudyFlorida Power & LightCurrent status
513CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
514CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
515CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
516CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
517CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
518CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
519CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
520CharlotteSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
521DesotoSolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
522HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
523HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
524HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
525HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
526HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
527HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
528HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
529HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
530HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
531HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
532HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
533HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
534HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
535HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
536HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
537HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
538HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
539HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
540HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
541HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
542HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
543HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
544HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
545HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
546HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
547HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
548HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
549HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
550HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
551HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
552HendrySolar752023-01-06System Impact StudyFlorida Power & LightCurrent status
558HendrySolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
559HendrySolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
561HendrySolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
562HendrySolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
563HendrySolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
564CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
565CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
566CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
567CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
568CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
569CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
570CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
571CollierSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
593MartinSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
594Indian RiverSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
595St. LucieSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
596St. LucieSolar752023-07-25System Impact StudyFlorida Power & LightCurrent status
Storey BendOsceolaSolar752018-02-01System Impact StudyOrlando Utilities CommissionCurrent status
Harmony 2OsceolaSolar752020-12-09System Impact StudyOrlando Utilities CommissionCurrent status
Storey Bend SouthOsceolaSolar752024-02-14System Impact StudyOrlando Utilities CommissionCurrent status
101HillsboroughSolar752023-04-24Cluster StudyTampa Electric CompanyCurrent status
112HillsboroughSolar752024-03-31Cluster StudyTampa Electric CompanyCurrent status
121HillsboroughSolar752025-05-06Cluster StudyTampa Electric CompanyCurrent status
122HillsboroughSolar752025-05-06Cluster StudyTampa Electric CompanyCurrent status
193LevySolar702017-08-11Facility StudyDuke Energy FloridaCurrent status
419MartinGas602020-09-18Facility StudyFlorida Power & LightCurrent status
Taylor Creek TwoOrangeSolar602024-02-14System Impact StudyOrlando Utilities CommissionCurrent status
76PolkSolar552020-11-30IA ExecutedTampa Electric CompanyCurrent status
111PolkSolar522024-03-27Cluster StudyTampa Electric CompanyCurrent status
JEA-Q007-PVDuvalSolar502017-12-21IA ExecutedJacksonville Electric AuthorityCurrent status
70PolkOther482020-05-21IA ExecutedTampa Electric CompanyCurrent status
120PolkBattery202025-05-05Cluster StudyTampa Electric CompanyCurrent status
123PolkSolar202025-05-06Cluster StudyTampa Electric CompanyCurrent status
FC100000PascoOther132024-12-04Facility StudyDuke Energy FloridaCurrent status
FC100379OrangeGas122025-11-25In Progress (unknown study)Duke Energy FloridaCurrent status
11Solar22015-08-11IA ExecutedSeminole Electric CooperativeCurrent status

Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem