Interconnection queue in Alabama

Data: Lawrence Berkeley National Laboratory and GridTracker, Queued Up, as of Dec 31, 2025.

This is an annual snapshot. A request's status may have changed since. Current status at Interconnection.fyi.

LBNL licenses the file CC BY 4.0, so project rows are shown and the file can be downloaded from our data library.

Statewide

Active capacity
8,501 MW
Active requests
48
Median years in queue (active)
0.7
Withdrawn, of requests entered by 2020
91%
Active capacity by type
TypeActive capacity (MW)Projects
Solar3,13921
Storage8494
Gas2,85810
Hybrid1,0545
Other6018

By county

Queue requests by county in Alabama, as of Dec 31, 2025
CountyActive capacity (MW)ProjectsSolarWindStorageGasHybridOtherMedian years in queue (active)Withdrawn, of requests entered by 2020
Mobile1,21642007212950.7
Colbert95821787806.283% of 29
Perry65644961602.8
Morgan52815280.4
Autauga47844780.7
Limestone471447111.4
Baldwin45934592.0
Jackson3992993000.895% of 21
Escambia39921992000.7
Greene39421951990.7
Lawrence39323936.3
Lee35123510.7
Dale20122010.7
Butler20012000.7
Bullock20012001.8
Dekalb20012003.4
Montgomery19911990.7
Cherokee17011700.7
Walker15011502.1
Houston13041300.8
Madison11011101.2
Clarke931930.7
Sumter751750.7
Monroe711710.7
Barbour00
Henry00
Marengo00
Macon00
Hale00
Lowndes00
Washington00
Shelby00
Calhoun00
Blount00
Tallapoosa00
Tuscaloosa00
Coosa00
Talladega00
Covington00
Dallas00
Pike00
Jefferson00
Russell00
Wilcox00
Etowah00
Chambers00
Cleburne00
Elmore00
Geneva00
Pickens00
Coffee00
Webb00
Conecuh00
Crenshaw00
Lamar00
Fayette00
Randolph00
Cullman00
Franklin00
Lauderdale00
Lake00
Caldwell00

Capacity is each request's first-listed capacity, so a hybrid's battery is not added on top. Most requests in a queue never get built.

Active requests

Status is as of Dec 31, 2025. Current status at Interconnection.fyi.

Active interconnection requests in Alabama
ProjectCountyTypeMWEntered the queueStudy phaseUtility or operatorLive status
416ColbertGas7802020-02-10IA ExecutedTennessee Valley AuthorityCurrent status
25-IC-1382MobileGas7072025-04-17Cluster StudySouthern CompanyCurrent status
25RSC-011MorganGas5282025-08-01In Progress (unknown study)Tennessee Valley AuthorityCurrent status
IC-1071PerrySolar3362022-09-27IA ExecutedSouthern CompanyCurrent status
25RSC-008JacksonBattery3002025-07-29In Progress (unknown study)Tennessee Valley AuthorityCurrent status
25-IC-1315MobileSolar+Battery2952025-04-08Cluster StudySouthern CompanyCurrent status
25-IC-1320ALeeGas2402025-04-11Facility StudySouthern CompanyCurrent status
25-IC-1317AutaugaGas2292025-04-11Cluster StudySouthern CompanyCurrent status
25-IC-1368MobileSolar2002025-04-17Cluster StudySouthern CompanyCurrent status
25-IC-1379ButlerSolar+Battery2002025-04-17Cluster StudySouthern CompanyCurrent status
25-IC-1380EscambiaSolar+Battery2002025-04-17Cluster StudySouthern CompanyCurrent status
IC-1266BullockSolar2002024-03-22IA ExecutedSouthern CompanyCurrent status
385LawrenceSolar2002019-08-01IA ExecutedTennessee Valley AuthorityCurrent status
514DekalbBattery2002022-08-24IA ExecutedTennessee Valley AuthorityCurrent status
25-IC-1356GreeneSolar+Battery1992025-04-16Facility StudySouthern CompanyCurrent status
25-IC-1358MontgomeryBattery1992025-04-16Cluster StudySouthern CompanyCurrent status
25-IC-1376BaldwinSolar1992025-04-17Cluster StudySouthern CompanyCurrent status
25-IC-1347EscambiaSolar1992025-04-16Cluster StudySouthern CompanyCurrent status
25-IC-1365GreeneSolar1952025-04-17Cluster StudySouthern CompanyCurrent status
405LawrenceSolar1932019-11-18IA ExecutedTennessee Valley AuthorityCurrent status
IC-1225BaldwinSolar1802024-01-02IA ExecutedSouthern CompanyCurrent status
387ColbertSolar1782019-08-01IA ExecutedTennessee Valley AuthorityCurrent status
25-IC-1361CherokeeSolar1702025-04-17Cluster StudySouthern CompanyCurrent status
25-IC-1370PerrySolar+Battery1602025-04-17Cluster StudySouthern CompanyCurrent status
254LimestoneNuclear1552014-08-15IA ExecutedTennessee Valley AuthorityCurrent status
255LimestoneNuclear1552014-08-15IA ExecutedTennessee Valley AuthorityCurrent status
256LimestoneNuclear1552014-08-15IA ExecutedTennessee Valley AuthorityCurrent status
IC-1210WalkerBattery1502023-12-08IA ExecutedSouthern CompanyCurrent status
25-IC-1318AutaugaGas1112025-04-11Cluster StudySouthern CompanyCurrent status
25-IC-1319AutaugaGas1112025-04-11Cluster StudySouthern CompanyCurrent status
25-IC-1321LeeGas1112025-04-11Cluster StudySouthern CompanyCurrent status
25-IC-1366DaleSolar1102025-04-17Cluster StudySouthern CompanyCurrent status
662MadisonSolar1102024-10-01Cluster StudyTennessee Valley AuthorityCurrent status
660JacksonSolar992024-10-01Cluster StudyTennessee Valley AuthorityCurrent status
25-IC-1336ClarkeSolar932025-04-14Cluster StudySouthern CompanyCurrent status
25-IC-1354DaleSolar912025-04-16Cluster StudySouthern CompanyCurrent status
IC-1224BaldwinSolar802024-01-02IA ExecutedSouthern CompanyCurrent status
IC-1127PerrySolar802023-03-03IA ExecutedSouthern CompanyCurrent status
IC-1128PerrySolar802023-03-03IA ExecutedSouthern CompanyCurrent status
25-IC-1360SumterSolar752025-04-16Cluster StudySouthern CompanyCurrent status
25-IC-1357MonroeSolar712025-04-16Cluster StudySouthern CompanyCurrent status
25-IC-1307HoustonNuclear502025-04-01Cluster StudySouthern CompanyCurrent status
25-IC-1309HoustonNuclear502025-04-01Cluster StudySouthern CompanyCurrent status
IC-1012AutaugaGas272020-10-15System Impact StudySouthern CompanyCurrent status
25-IC-1306HoustonNuclear152025-04-01Cluster StudySouthern CompanyCurrent status
25-IC-1308HoustonNuclear152025-04-01Cluster StudySouthern CompanyCurrent status
25-IC-1344MobileGas142025-04-15Cluster StudySouthern CompanyCurrent status
625LimestoneNuclear62024-06-12Cluster StudyTennessee Valley AuthorityCurrent status

Lawrence Berkeley National Laboratory and GridTracker · Queued Up: Interconnection Queue Data File (Lawrence Berkeley National Laboratory) · data for 2025 · as of May 7, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent