Power plant · EIA plant code 96

Beluga

Operator
Chugach Electric Assn Inc
Location
Kenai Peninsula, AK (county level only)
Balancing authority
Not reported
Nameplate capacity
312.4 MW
Summer capacity
300.4 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
-3,402 MWh
Capacity factor
Net consumer of energy

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
5,744 metric tons
Carbon dioxide per MWh
24,120 lb/MWh

eGRID reports 6,331 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Beluga
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Natural Gas Fired Combustion TurbineNG16 MW1968Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
2Natural Gas Fired Combustion TurbineNG16 MW1968Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
3Natural Gas Fired Combustion TurbineNG59.1 MW1972Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
5Natural Gas Fired Combustion TurbineNG68.3 MW1975Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
6Natural Gas Fired Combustion TurbineNG76.5 MW1976Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
7Natural Gas Fired Combustion TurbineNG76.5 MW1978Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent