gridprims

Power plant · EIA plant code 7710

H Allen Franklin Combined Cycle

Operator
Southern Power Co
Location
Lee, AL (county level only)
Balancing authority
Southern Company Services, Inc. - Trans (SOCO)
Nameplate capacity
1,995.7 MW
Summer capacity
1,901.8 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
12,061,177 MWh
Capacity factor
69.0%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
5,073,182 metric tons
Carbon dioxide per MWh
817 lb/MWh

eGRID reports 5,592,225 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at H Allen Franklin Combined Cycle
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
CT1ANatural Gas Fired Combined CycleNG203.1 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
CT1BNatural Gas Fired Combined CycleNG203.1 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
CT2ANatural Gas Fired Combined CycleNG203.1 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
CT2BNatural Gas Fired Combined CycleNG203.1 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
CT3ANatural Gas Fired Combined CycleNG203.1 MW2008Operable · As of September 2026 (EIA-860M): (OP) Operating
CT3BNatural Gas Fired Combined CycleNG203.1 MW2008Operable · As of September 2026 (EIA-860M): (OP) Operating
ST1Natural Gas Fired Combined CycleNG213.3 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
ST2Natural Gas Fired Combined CycleNG281.9 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
ST3Natural Gas Fired Combined CycleNG281.9 MW2008Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem