gridprims

Power plant · EIA plant code 7030

Major Oak Power

Operator
Major Oak Power, LLC
Location
Robertson, TX (county level only)
Balancing authority
Electric Reliability Council of Texas, Inc. (ERCO)
Nameplate capacity
349.2 MW
Summer capacity
305 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
2,230,399 MWh
Capacity factor
72.9%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
2,658,316 metric tons
Carbon dioxide per MWh
2,527 lb/MWh

eGRID reports 2,930,291 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Major Oak Power
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Conventional Steam CoalLIG174.6 MW1990Operable · As of September 2026 (EIA-860M): (OP) Operating
2Conventional Steam CoalLIG174.6 MW1991Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.