gridprims

Power plant · EIA plant code 66567

HEBHoustonDistributionCenter

Operator
Texas Microgrid, LLC
Location
Harris, TX (county level only)
Balancing authority
Electric Reliability Council of Texas, Inc. (ERCO)
Nameplate capacity
12.8 MW
Summer capacity
12.8 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
8,102 MWh
Capacity factor
7.2%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
5,733 metric tons
Carbon dioxide per MWh
1,872 lb/MWh

eGRID reports 6,319 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at HEBHoustonDistributionCenter
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
HDC10Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC11Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC12Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC13Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC14Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC15Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC16Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC17Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC18Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC19Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC20Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC21Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC22Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC23Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC24Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC25Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC26Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC27Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC28Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC29Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC30Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC31Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HDC32Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC1Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC2Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC3Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC4Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC5Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC6Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC7Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC8Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating
HHDC9Natural Gas Internal Combustion EngineNG0.4 MW2021Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0