Power plant · EIA plant code 66513

MA Acushnet 540R Main St

Operator
TJA 540R Main St. Acushnet, LLC
Location
Bristol, MA (county level only)
Balancing authority
ISO New England Inc. (ISNE)
Nameplate capacity
0 MW
Summer capacity
0 MW

Planned changes reported to EIA: 2 proposed generators.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
Not reported
Capacity factor
No EIA-923 generation for 2025

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

This plant is not in eGRID2023 (revision 2).

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at MA Acushnet 540R Main St
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
18229Solar PhotovoltaicSUN4 MWProposed, planned start 2027 · As of September 2026 (EIA-860M): (L) Regulatory approvals pending. Not under construction
B8229BatteriesMWH2 MWProposed, planned start 2027 · As of September 2026 (EIA-860M): (L) Regulatory approvals pending. Not under construction

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0