gridprims

Power plant · EIA plant code 65978

Dania Beach 7

Operator
Florida Power & Light Co
Location
Broward, FL (county level only)
Balancing authority
Florida Power & Light Company (FPL)
Nameplate capacity
1,447.7 MW
Summer capacity
1,246 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
6,087,686 MWh
Capacity factor
48.0%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

This plant is not in eGRID2023 (revision 2).

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Dania Beach 7
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
7GT1Natural Gas Fired Combined CycleNG492.2 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating
7GT2Natural Gas Fired Combined CycleNG492.2 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating
ST7Natural Gas Fired Combined CycleNG463.3 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0