gridprims

Power plant · EIA plant code 64210

Bellefield Solar and Energy Storage Farm

Operator
50LW 8me LLC
Location
Kern, CA (county level only)
Balancing authority
California Independent System Operator (CISO)
Nameplate capacity
1,000 MW
Summer capacity
1,000 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
57,898 MWh
Capacity factor
7.8%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

This plant is not in eGRID2023 (revision 2).

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Bellefield Solar and Energy Storage Farm
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
50LWASolar PhotovoltaicSUN500 MW2025Operable · As of September 2026 (EIA-860M): (OP) Operating
50LWBBatteriesMWH500 MW2025Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent