gridprims

Power plant · EIA plant code 62745

Wheatridge Hybrid

Operator
Wheatridge Wind Holdings, LLC
Location
Morrow, OR (county level only)
Balancing authority
Bonneville Power Administration (BPAT)
Nameplate capacity
280 MW
Summer capacity
280 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
668,296 MWh
Capacity factor
27.2%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

eGRID2023 (revision 2) reports no carbon dioxide for this plant.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Wheatridge Hybrid
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
BTRYBatteriesMWH30 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating
SOLARSolar PhotovoltaicSUN50 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating
WINDOnshore Wind TurbineWND200 MW2020Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.