gridprims

Power plant · EIA plant code 62564

Elkhorn Battery Energy Storage System

Operator
Pacific Gas & Electric Co.
Location
Monterey, CA (county level only)
Balancing authority
California Independent System Operator (CISO)
Nameplate capacity
182.5 MW
Summer capacity
182.5 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
-2,226 MWh
Capacity factor
Net consumer of energy

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

eGRID2023 (revision 2) reports no carbon dioxide for this plant.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Elkhorn Battery Energy Storage System
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
ELKHOBatteriesMWH182.5 MW2022Operable · As of September 2026 (EIA-860M): (OA) Out of service but expected to return to service in next calendar year

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent