gridprims

Power plant · EIA plant code 57322

Mont Belvieu Cogeneration Unit

Operator
Targa Co-Generation LLC
Location
Chambers, TX (county level only)
Balancing authority
Electric Reliability Council of Texas, Inc. (ERCO)
Nameplate capacity
15 MW
Summer capacity
12.3 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
76,810 MWh
Capacity factor
58.5%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
27,504 metric tons
Carbon dioxide per MWh
630 lb/MWh

eGRID reports 30,318 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Mont Belvieu Cogeneration Unit
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
GT01Natural Gas Fired Combustion TurbineNG15 MW2009Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent