gridprims

Power plant · EIA plant code 52149

West Point (PA)

Operator
Merck & Co Inc-West Point
Location
Montgomery, PA (county level only)
Balancing authority
PJM Interconnection, LLC (PJM)
Nameplate capacity
90.6 MW
Summer capacity
81.5 MW

Planned changes reported to EIA: 1 proposed generator.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
265,337 MWh
Capacity factor
33.4%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
0 metric tons
Carbon dioxide per MWh
0 lb/MWh

eGRID reports 0 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at West Point (PA)
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
COG3Natural Gas Fired Combustion TurbineNG38.4 MW2001Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN14Natural Gas Internal Combustion EngineNG1.5 MW2016Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN15Natural Gas Internal Combustion EngineNG1.3 MW2017Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN16Natural Gas Internal Combustion EngineNG1.3 MW2020Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN17Natural Gas Internal Combustion EngineNG2 MW2022Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN18Natural Gas Internal Combustion EngineNG2.5 MW2024Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN19Natural Gas Internal Combustion EngineNG1 MW2024Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN2Natural Gas Fired Combustion TurbineNG32.3 MW1989Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN20Natural Gas Internal Combustion EngineNG2 MW2024Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GEN21Natural Gas Internal Combustion EngineNG2.5 MWProposed, planned start 2026 · As of September 2026 (EIA-860M): (V) Under construction, more than 50 percent complete
GEN3Petroleum LiquidsDFO2.5 MW1972Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
GEN5Petroleum LiquidsDFO1.2 MW1994Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
GEN8Natural Gas Internal Combustion EngineNG1 MW1999Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
GEN9Natural Gas Internal Combustion EngineNG1.3 MW2004Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GN10Natural Gas Internal Combustion EngineNG1.3 MW2004Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
GN11Petroleum LiquidsDFO1 MW2010Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem