gridprims

Power plant · EIA plant code 2312

Wayne IC

Operator
City of Wayne (NE)
Location
Wayne, NE (county level only)
Balancing authority
Southwest Power Pool (SWPP)
Nameplate capacity
21.8 MW
Summer capacity
20.2 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
141 MWh
Capacity factor
0.1%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
40 metric tons
Carbon dioxide per MWh
1,956 lb/MWh

eGRID reports 44 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Wayne IC
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Petroleum LiquidsDFO1.3 MW1951Operable · As of September 2026 (EIA-860M): (OP) Operating
2Petroleum LiquidsDFO1 MW1947Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
3Petroleum LiquidsDFO1.9 MW1956Operable · As of September 2026 (EIA-860M): (OP) Operating
4Petroleum LiquidsDFO2 MW1960Operable · As of September 2026 (EIA-860M): (OP) Operating
5Petroleum LiquidsDFO3.5 MW1966Operable · As of September 2026 (EIA-860M): (OP) Operating
6Petroleum LiquidsDFO5.1 MW1968Operable · As of September 2026 (EIA-860M): (OP) Operating
7Petroleum LiquidsDFO3.5 MW1998Operable · As of September 2026 (EIA-860M): (OP) Operating
8Petroleum LiquidsDFO3.5 MW1998Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent