gridprims

Power plant · EIA plant code 10487

International Falls Power

Operator
Boise White Paper LLC
Location
Koochiching, MN (county level only)
Balancing authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Nameplate capacity
14.2 MW
Summer capacity
14.2 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
48,054 MWh
Capacity factor
38.6%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

eGRID2023 (revision 2) reports no carbon dioxide for this plant.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at International Falls Power
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
GEN1Conventional HydroelectricWAT2.2 MW1946Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN2Conventional HydroelectricWAT2.2 MW1946Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN3Conventional HydroelectricWAT2.2 MW1946Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN4Conventional HydroelectricWAT2.2 MW1946Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN5Conventional HydroelectricWAT2.2 MW1946Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN6Conventional HydroelectricWAT1.6 MW1924Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN7Conventional HydroelectricWAT1.6 MW1924Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.