gridprims

Power plant · EIA plant code 10213

El Segundo Cogen

Operator
Chevron USA Inc-El Segundo
Location
Los Angeles, CA (county level only)
Balancing authority
California Independent System Operator (CISO)
Nameplate capacity
180.1 MW
Summer capacity
171.6 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
1,216,454 MWh
Capacity factor
77.1%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
636,967 metric tons
Carbon dioxide per MWh
1,216 lb/MWh

eGRID reports 702,136 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at El Segundo Cogen
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
GEN1Natural Gas Fired Combined CycleNG42.4 MW1987Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN2Natural Gas Fired Combined CycleNG42.4 MW1987Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN5Natural Gas Fired Combined CycleNG40.3 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN6Natural Gas Fired Combined CycleNG9.1 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN7Natural Gas Fired Combined CycleNG40.7 MW2013Operable · As of September 2026 (EIA-860M): (OP) Operating
GEN8Natural Gas Fired Combined CycleNG5.2 MW2013Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent