Power plant · EIA plant code 10

Greene County

Operator
Alabama Power Co
Location
Greene, AL (county level only)
Balancing authority
Southern Company Services, Inc. - Trans (SOCO)
Nameplate capacity
1,288.4 MW
Summer capacity
1,256.1 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
1,100,429 MWh
Capacity factor
9.8%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
796,395 metric tons
Carbon dioxide per MWh
1,257 lb/MWh

eGRID reports 877,875 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Greene County
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Natural Gas Steam TurbineNG299.2 MW1965Operable · As of September 2026 (EIA-860M): (OP) Operating
2Natural Gas Steam TurbineNG269.2 MW1966Operable · As of September 2026 (EIA-860M): (OP) Operating
GT10Natural Gas Fired Combustion TurbineNG80 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
GT2Natural Gas Fired Combustion TurbineNG80 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
GT3Natural Gas Fired Combustion TurbineNG80 MW1995Operable · As of September 2026 (EIA-860M): (OP) Operating
GT4Natural Gas Fired Combustion TurbineNG80 MW1995Operable · As of September 2026 (EIA-860M): (OP) Operating
GT5Natural Gas Fired Combustion TurbineNG80 MW1995Operable · As of September 2026 (EIA-860M): (OP) Operating
GT6Natural Gas Fired Combustion TurbineNG80 MW1995Operable · As of September 2026 (EIA-860M): (OP) Operating
GT7Natural Gas Fired Combustion TurbineNG80 MW1995Operable · As of September 2026 (EIA-860M): (OP) Operating
GT8Natural Gas Fired Combustion TurbineNG80 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
GT9Natural Gas Fired Combustion TurbineNG80 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent